Planning Permission Ireland
GrantedEnergyDecided 29 September 2025

Cornacarta Doonacurry Foygh Kilcommock Glebe Ledwithstown and Tirlickeen (townlands), Keenagh and Ballymahon, County Longford

A 10-year permission for a major solar farm and energy storage compound across multiple townlands.

2460325 · Longford County Council · Lodged 20 December 2024

Reference
2460325
Authority
Longford County Council
Register status
Appealed
Type
PERMISSION
Received
20 December 2024

Summary

AI-generated

This large-scale development spans approximately 130 hectares and features 661,500 sq m of solar panels on ground-mounted frames. The project includes 42 transformer stations, an energy storage compound with 38 battery modules, underground cabling, and a river crossing.

Energysolarbattery storagerenewable

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

A 10 year planning permission for a solar farm and energy storage compound with a total area of circa 130 hectares. The proposed development will consist of a solar farm comprising of c. 661,500 sq. M of solar photovoltaic panels on ground mounted frames, associated string inverters mounted to rear of panels and 42 no. Single storey electrical transformer stations. The proposed development includes an energy storage compound consisting of 38 no. Containerised energy storage modules and associated plant and equipment, 10 no. Transformers, 2 no. Auxiliary transformers, 1 no. Medium voltage control / switching substation and 1 no. Spare parts container. The proposed development will also include underground electrical ducting and cabling within the development site and within the l1139, l1137, l1135, r392 and l1132 public roads, and crossing of the royal canal (either by open trench or horizontal directional drill), temporary construction compounds, security fencing, cctv, access tracks (including clear span bridge over donacurry river), landscaping, drainage and all ancillary development works and apparatus necessary to facilitate the proposed development. Construction and operational access will be via 5 no. Existing entrances from the l1139, l1137, l1135 and l1132 which will be upgraded and 2 no. New entrances from the l11351. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. A natura impact statement (nis) has been prepared and will be submitted to the planning authority with the application

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Foigha, Keenagh, Co. LongfordJan 2025€400,000309 m
Cornacarta, Ballymahon, Co. Longfordnot full market priceAug 2025€90,000355 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received20 December 2024
  2. Further information requested20 February 2025
  3. Further information received25 July 2025
  4. Decision due29 September 2025
  5. Decision issued29 September 2025
  6. Appeal submitted17 October 2025

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.