Continued operation of Edenderry Power Plant exclusively using sustainable biomass fuel until 2030.

21291 · Offaly County Council · Lodged 10 May 2021

Reference
21291
Authority
Offaly County Council
Register status
Decided
Type
PERMISSION
Received
10 May 2021

Summary

AI-generated

The application proposes to increase the volume of biomass consumed at the facility from 300,000 to 530,000 tonnes per year. The development will utilise existing infrastructure with no changes to the permitted boundary or site entrances.

Energypower plantbiomassrenewables

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Development at edenderry power plant. Edenderry power limited currently has planning permission to operate edenderry power plant as a peat and biomass co-fired power plant under grant of planning permission (offaly county council register reference - pl2/15/129, an bord pleanála register reference - pl 19.245295). The proposed development will consist of the continued operation of edenderry power plant from the beginning of 2024 to the end of 2030 exclusively using sustainable biomass fuel. The applicant proposes to increase the volume of biomass consumed at the facility from a current maximum of 300,000 to 530,000 tonnes per annum. It is proposed to utilise the existing permitted electricity generation station and infrastructure, including fuel handling systems, utilities, processing systems and ancillary structures as part of the proposed development. There will be no change to existing infrastructure present on-site. Site access and egress will use the existing permitted site entrances to the r401 public road. There will be no change to the permitted boundary of the facility. Edenderry power plant is licenced by the environmental protection agency under an industrial emissions (ie) licence [ref. P0482-04]. Activities at the facility and associated environmental aspects and emissions will continue to be regulated and controlled by the epa. The planning application is accompanied by an environmental impact assessment report (eiar). The planning application is also accompanied by a natura impact statement (nis)

Key dates

Timeline

  1. Application received10 May 2021
  2. Further information requested2 July 2021
  3. Further information received19 November 2021
  4. Decision due28 March 2022
  5. Decision issued25 March 2022
  6. Grant issued5 May 2022
  7. Permission expiry31 December 2030

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.