Planning Permission Ireland
GrantedInfrastructureDecided 11 June 2025

Kilmalogue Park and Kilmalogue and Shanderry, Portarlington, County Offaly

Temporary construction access and wall removal to facilitate a permitted solar farm substation.

2560018 · Offaly County Council · Lodged 23 January 2025

Reference
2560018
Authority
Offaly County Council
Register status
Decided
Type
PERMISSION
Received
23 January 2025

Summary

AI-generated

The development consists of creating a temporary vehicular access and construction track by temporarily removing a 5.4-metre section of boundary wall. This will facilitate the construction of a previously permitted 10KV substation for a solar farm, with the wall to be fully reinstated afterwards.

Infrastructuresolarinfrastructuresubstation

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The development will consist of the creation and use of a temporary vehicular access onto the public carriageway at kilmalogue park for use for the construction of a permitted 10kv single storey substation and its associated operational access track both previously permitted under planning ref. No. 17/275 as revised by planning ref. 23/196 as part of a solar farm development. The proposed development will comprise the temporary removal of a section of an existing boundary wall (c. 5.4m) at kilmalogue park, the provision of a temporary construction track, ancillary development works, full reinstatement of the wall upon completion of the construction of the permitted substation and an increase in the area of permanent gravel track around the substation. The development will be used for the construction of the permitted substation in lieu of a previously permitted construction access track permitted under planning ref. No. 17/275 for the construction of the substation.

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
34 Na Cluainte, Portarlington, OffalyApr 2025€240,000212 m
72 Na Cluainte, Tullamore Rd, PortarlingtonOct 2025€237,000222 m
69 Na Cluainte, Tullamore Rd, PortarlingtonAug 2025€255,000244 m
38 Na Cluainte, Portarlington, OffalyApr 2026€275,000274 m
83 Na Cluainte, Portarlington, OffalyJan 2025€240,000279 m
60 Na Cluainte, Tullamore Rd, PortarlingtonMay 2026€270,000296 m
21 Shandra Woods, Portarlington, OffalyMar 2026€295,000326 m
18 Shandra Woods, Tullamore Road, PortarlingtonApr 2025€260,000347 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received23 January 2025
  2. Further information requested18 March 2025
  3. Further information received15 May 2025
  4. Decision due11 June 2025
  5. Decision issued11 June 2025
  6. Grant issued17 July 2025
  7. Permission expiry16 July 2030

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.