Installation of 22.25km of underground electricity cable between Bunkimalta Wind Farm and Nenagh.
16600433 · Tipperary County Council · Lodged 11 May 2016
- Reference
- 16600433
- Authority
- Tipperary County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 11 May 2016
Summary
AI-generatedThe project involves installing approximately 22.25km of 38kV underground cable primarily within public roads. This cable will connect the Bunkimalta Wind Farm to the Nenagh 110kV substation and is accompanied by a Natura Impact Statement.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Installation of approximately 22.25km of 38kv underground cable (ugc) between bunkimalta wind farm and nenagh 110kv substation, to be installed primarily in public roads. The application is accompanied by a natura impact statement (nis)
Key dates
Timeline
- Application received11 May 2016
- Further information requested4 July 2016
- Further information received10 April 2017
- Decision due4 June 2017
- Decision issued29 May 2017
- Grant issued3 July 2017
- Permission expiry2 July 2022
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
Re-sagging (“re-tensioning”) of the existing conductor along an approximate distance of 16km of the Maynooth…
Hollywood Lower Hollywood Upper Hollywood Demesne Slievecorragh Toor Lugglass Upper Coonmore Lugglass Lower Knocknaboley Granamore Knocknadroose Oakwood Ballinagee Brockagh and Sevenchurches or Camaderry. , Co. Wicklow
2560469WicklowLodged 26 Jun 2025
- RefusedInfrastructure
Development of circa 10km of grid connection infrastructure on the public road (N72) to connect the approved…
Killadangan Ballymacmague Sth Ballymacmague Nth Ballylemon Lwr Knockacullen , Ballylemon Killeeshal Ballynamintra Upr Cappagh Kilcannon (Osbourne) , Kilcannon (Hely) Ballynahemery Rockfield Bawnnavinnoge Kilcoher
21735WaterfordLodged 29 Jul 2021
- GrantedInfrastructure
Permission for the replacement of 2 no. existing 110kV electricity supply towers with 2 no. new towers (steel…
Site of approx. 1.09ha to the south of Ballyman Road, Co Dublin
D16A/0661Dún Laoghaire–RathdownLodged 6 Apr 2017
- RefusedEnergy
Permission for: The construction of one 4.2 MW wind turbine with overall tip height of up to 150m; The…
Kilcash , Co Roscommon
21221RoscommonLodged 30 Apr 2021
- GrantedEnergy
For the development consisting of a wind energy development comprising of one electricity generating wind…
Cloonascragh , Tuam , Co. Galway
221175galwayLodged 17 Nov 2022
- GrantedEnergy
25 year permission for a single electricity generating wind turbine with an overall maximum height of up to…
Mullafarry and Tawnaghmore Lower , Killala , Co. Mayo
19260MayoLodged 15 Apr 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.