Coolnashinnagh Ardagh Gortfree and Bolakeale, Co. Tipperary
Installation of a 2.25km underground grid connection for a wind farm in Tipperary.
211068 · Tipperary County Council · Lodged 22 July 2021
- Reference
- 211068
- Authority
- Tipperary County Council
- Register status
- Invalid or incomplete
- Type
- PERMISSION
- Received
- 22 July 2021
Summary
AI-generatedPermission is sought for a 10-year period to install 2.25km of 38kV underground grid connection cabling and ducting. This forms part of a larger 33.8km grid connection serving an approved 9-turbine wind farm, with the remainder of the line subject to a separate application in Kilkenny.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A ten year appropriate period planning permission for the installation of 2.25km of 38kv underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments in the townlands of coolnashinnagh, ardragh, bolakeale & gortfree, co. Tipperary. Advisory note: the full extent of the grid connection is 33.8km, and a separate planning application will be made for an underground grid connection to kilkenny county council. This development comprises park of an overall development for which planning permission was granted for a 9-turbine wind farm and all associated works on lands located in the townlands of farranrory upper, farranrory lower, coolnashinnagh & gortnasmuttan, co. Tipperary. The planning application will be accompanied by an environmental impact assessment report (eiar) and natura impact statement
Key dates
Timeline
- Application received22 July 2021
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decision30 m away
A ten-year appropriate period planning permission for development of this site: the proposed development will…
Coolanshinnagh Ardragh Gortfree Bolakeale , Co. Tipperary
211558TipperaryLodged 22 Oct 2021Infrastructure
- Awaiting decision40 m away
An amendment planning application for a planning application granted under reference PL/21/1620 in the…
Various townlands - Coolanshinnagh Ardragh Gortfree Bolakeale , , Co Tipperary.
2360367TipperaryLodged 31 May 2023Infrastructure
- Granted50 m away
A) an increase to the footprint of the substation compound of 381.6m2, b) an increase to the footprint of the…
Coolnashinnagh , Ballingarry Thurles , Co. Tipperary
2460280TipperaryLodged 16 Apr 2024Infrastructure
- Awaiting decision290 m away
A ten year planning permission for a renewable energy development with a 40-year operational life (from the…
Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun , Co. Tipperary
20913TipperaryLodged 17 Aug 2020Energy
- Awaiting decision440 m away
A temporary Meteorological Mast and associated site works that will operate for a further 3 years. The…
Farranrory Upper , BALLINGARRY , Co Tipperary
2260554TipperaryLodged 13 Oct 2022Retention
- Granted490 m away
A dwelling, domestic garage, entrance, bore well, install waste water treatment system including associated…
Garrynagree , The Commons , Thurles
19600105TipperaryLodged 8 Feb 2019New dwelling
- Granted490 m away
A temporary Meteorological Mast and associated site works that will operate for a further 3 years, it will…
Farranrory Upper , Ballingarry , Co Tipperary
2260696TipperaryLodged 14 Dec 2022Retention
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
A ten year appropriate period planning permission for the installation of 2.25km of 38kV underground grid…
Coolnashinnagh Ardagh Gortfree and Bolakeale , Co. Tipperary
211097TipperaryLodged 27 Jul 2021
- Awaiting decisionInfrastructure
A ten-year appropriate period planning permission for development of this site: the proposed development will…
Coolanshinnagh Ardragh Gortfree Bolakeale , Co. Tipperary
211558TipperaryLodged 22 Oct 2021
- GrantedInfrastructure
For a ten-year appropriate period planning permission for development of this site; the proposed development…
Killeen , Co. Kilkenny
21627KilkennyLodged 22 Jul 2021
- Awaiting decisionInfrastructure
An amendment planning application for a planning application granted under reference PL/21/1620 in the…
Various townlands - Coolanshinnagh Ardragh Gortfree Bolakeale , , Co Tipperary.
2360367TipperaryLodged 31 May 2023
- Awaiting decisionEnergy
A ten year planning permission for a renewable energy development with a 40-year operational life (from the…
Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun , Co. Tipperary
20913TipperaryLodged 17 Aug 2020
- Awaiting decisionEnergy
For a 10-year planning permission for a new 38kV substation. The development for which planning permission is…
Killeen , Co. Kilkenny
20517KilkennyLodged 7 Aug 2020
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.