Beaumont Hospital capital works to sequence oncology extension before permitted emergency department
Saturday 21 November 2026
Capital development at Beaumont Hospital will prioritise an oncology extension and inpatient block ahead of a permitted emergency department, the Dáil has heard.
Capital development at Beaumont Hospital will prioritise a radiation oncology extension and inpatient bed block before delivering a permitted new emergency department, the Tánaiste has confirmed.
Speaking during Dáil questions, Tánaiste Simon Harris addressed capital project delivery at the Dublin hospital following queries from Deputy Barry Heneghan regarding project sequencing and construction timelines.
Deputy Heneghan noted that while planning permission for a new emergency department was granted in May 2025, parliamentary replies indicated a construction delivery timeframe of the second quarter of 2030. He highlighted that project sequencing prioritises radiation oncology first, followed by a 95-bed inpatient block, and then the emergency department.
The Tánaiste confirmed that Beaumont Hospital management determined the delivery sequence based on clinical priority. Enabling works are under way on the radiation oncology centre extension, with main construction expected to commence in 2027. This will be followed by the new inpatient ward block, located near the oncology development, requiring phased works to minimise operational disruption.
In the interim, emergency capacity will be expanded through a two-storey modular extension designed to enlarge reception and waiting areas and release clinical space. The Tánaiste confirmed that a main contractor has been appointed for the modular project, with site mobilisation and construction commencement under way.