Galway County Council is preparing to serve notices to treat for 54 homes along the Galway City Ring Road following the withdrawal of the final judicial review.
Galway County Council will issue notices to treat for the Galway Ring Road after the final judicial review was withdrawn, the Dáil has heard.
Speaking during a Topical Issue debate, Deputy Seán Kyne stated that 54 homes are subject to compulsory purchase orders (CPOs) for the major infrastructure project. Formal notice to treat letters are scheduled to issue in early January, though the local authority has already begun voluntary early acquisition negotiations.
According to figures shared in the debate, five homeowners have settled with Galway County Council and Transport Infrastructure Ireland (TII), six are at an advanced stage of negotiations, and three cases are under assessment. Kyne also noted that local authorities will consider affected homeowners as having qualifying housing need under development plans should they seek planning permission to rebuild locally.
Minister of State Emer Higgins confirmed that the road development was approved with conditions by An Coimisiún Pleanála in April 2026 after an updated environmental impact assessment report was submitted in April 2025. Five applications for judicial review were lodged, with the final challenge withdrawn in November 2026, clearing the council to progress the scheme.
Higgins outlined that once a notice to treat is formally served, affected parties can submit compensation claims, followed by valuer negotiations. If landowners and the acquiring authority fail to reach an agreement on compensation, the matter can be referred to statutory arbitration.