Planning Permission Ireland
GrantedEnergyDecided 9 August 2022

Kildreenagh, Bagenalstown, Co. Carlow

Erection of a 65m wind turbine and electrical substation in Bagenalstown.

21254 · Carlow County Council · Lodged 5 July 2021

Reference
21254
Authority
Carlow County Council
Register status
Decided
Type
PERMISSION
Received
5 July 2021
Residential units
1
Floor area
25 m²

Summary

AI-generated

Permission is sought for the erection of one wind turbine with a hub height of 65m and a blade length of 23.5m. The development also includes a 25 sq. m electrical substation and a site access road.

Energywind turbinerenewable energysubstation

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Permission for the erection of 1 no. Wind turbine (hub height 65m, blade length 23.5m), and the construction of a 25.00 sq. M electrical substation, site access road, and all ancillary works

Key dates

Timeline

  1. Application received5 July 2021
  2. Further information requested24 August 2021
  3. Further information received27 June 2022
  4. Decision due9 August 2022
  5. Decision issued9 August 2022
  6. Appeal submitted1 September 2022
  7. Appeal decided12 September 2023
  8. Permission expiry11 September 2028

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.