Planning Permission Ireland
GrantedIndustrialDecided 22 June 2022

Milltown, Garryhill, Co. Carlow

Construction of a new 900 square metre light industrial storage unit at Garryhill.

21363 · Carlow County Council · Lodged 27 September 2021

Reference
21363
Authority
Carlow County Council
Register status
Decided
Type
PERMISSION
Received
27 September 2021

Summary

AI-generated

The project consists of the construction of a new light industrial storage unit with a floor area of 900 square metres. The development will also include all associated site development works.

Industrialindustrialstoragewarehouse
Floor area
900 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Permission for the construction of a new 900 sq. M light industrial storage unit together with all associated site development works

Key dates

Timeline

  1. Application received27 September 2021
  2. Further information requested18 November 2021
  3. Further information received23 December 2021
  4. Decision due22 June 2022
  5. Decision issued22 June 2022
  6. Grant issued14 February 2024
  7. Appeal submitted14 July 2022
  8. Appeal decided14 February 2024
  9. Permission expiry13 February 2029

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.