Shankill Upper, Co Cavan
Construction of a 38kV transmission line connecting a proposed substation to an existing substation.
16109 · Cavan County Council · Lodged 7 March 2016
- Reference
- 16109
- Authority
- Cavan County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 7 March 2016
Summary
AI-generatedThe project involves the construction of a 38kV transmission line in County Cavan. The line will run from a proposed substation in the townland of Aghaway, crossing multiple townlands, to connect with an existing substation in Shankill Upper.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
The construction of a 38kv transmission line from the proposed substation in the townland of aghaway (county cavan planning register reference 15/84 and an bord pleanala reference pl 02.245716); and across the townlands of aghaway, aghradrumgowna or calf field, knockatudor, tullycoe, drumhallagh, lisegny, killnagarrbet, lisatawan, larah, clondargan glebe, lisatoo, drumcrow, countenan, raskill, broughderg, drumnanarragh, clonervy and shankill upper, to an existing substation
Key dates
Timeline
- Application received7 March 2016
- Further information requested26 April 2016
- Further information received9 June 2016
- Decision due6 July 2016
- Decision issued30 June 2016
- Grant issued5 August 2016
- Permission expiry4 August 2021
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
For development to erect a permanent meteorological mast, with a maximum height of 76 metres, for the purpose…
Aghaway , Co. Cavan
16336CavanLodged 7 Jul 2016Energy
- Granted30 m away
For development consisting of: A 10 year permission for the construction of an energy storage system…
Aghaway (Larah North ED) , Co. Cavan
20268CavanLodged 3 Jul 2020Energy
- Granted40 m away
For increased fence height from that granted under Pl. Ref. 15/84 and all ancillary works at Aghaway 38KV…
Aghaway , Cootehill , Co. Cavan
18286CavanLodged 2 Jul 2018Retention
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedInfrastructure
Of technical amendments to the 38kV substation and associated compound permitted under Cavan County Council…
Taghart South , Shercock , Co Cavan
1936CavanLodged 7 Feb 2019
- GrantedInfrastructure
Consist of Planning Permission to build a 38kV overhead line from a point in the Townland of Cargaghoge and…
Tullynamalra , Castleblayney , Co Monaghan
169014MonaghanLodged 21 Mar 2016
- GrantedInfrastructure
For development consisting of the installation of approximately 9km of 38 kV underground electricity…
Taghart South Corlea Cornamagh Collops Corglass Drumsallagh Corawaddy Carnagee Cornakill Dunaree Lisanisky Lisasturrin Corgarry and Larchfield Glebe , Co. Cavan
17502CavanLodged 29 Nov 2017
- GrantedInfrastructure
The development will consist of: the installation of approximately 4km of underground electricty transmission…
Drumgill Cornahoova Corratober , Ardagh & Meath Hill , Co. Meath
KA171177MeathLodged 9 Oct 2017
- GrantedInfrastructure
Erection of 38kV Line(s) and alteration to existing 38kV Line at Ballylicky, Barnagearagh, Ardnacloghy,…
Ballylicky etc., , ,
081495corkLodged 12 Aug 2008
- GrantedInfrastructure
Permission for the construction of a 38kv electricity substation, switchroom and equipment compound with…
Luppan County Monaghan and across the townlands of Shanmullagh Coraghbrack Drumlester Knockabeany Drumbristan Tonintlieve Cloghfin Derrykinnigh More Killybreen Killycarran Derrygola Tamlet Derrilla Tonyfinnigan Knockcor Drumdart Agha ,
18562MonaghanLodged 4 Dec 2018
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.