Planning Permission Ireland
GrantedEnergyDecided 23 May 2017

Carrickabane, Finea, Co. Cavan

Development of a 4.2MVA solar farm with ground-mounted panels and associated infrastructure in Finea.

16443 · Cavan County Council · Lodged 20 September 2016

Reference
16443
Authority
Cavan County Council
Register status
Decided
Type
PERMISSION
Received
20 September 2016

Summary

AI-generated

The development consists of a solar farm with an export capacity of approximately 4.2MVA. It will feature ground-mounted photovoltaic panels, an ESB terminal station, a switchgear enclosure, four inverter stations, perimeter fencing, and a new access point from the R194.

Energysolarrenewableinfrastructure
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

For the following development which will consist of a solar farm with an export capacity of approximately 4.2mva comprising photovoltaic panels on ground mounted frames, an enclosed single storey esb terminal station, a single storey switchgear enclosure and storage container, 4 no. Single storey inverter stations, ducting and underground electrical cabling, perimeter fencing, 11 no. Mounted cctv cameras, provision of new access from r194 (and internal access tracks), and all associated site development and landscaping works. Significant further information has been submitted

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Bracklagh Finea, Cavan, CavanDec 2025€285,000451 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received20 September 2016
  2. Further information requested10 November 2016
  3. Further information received27 April 2017
  4. Decision due24 May 2017
  5. Decision issued23 May 2017
  6. Appeal submitted16 June 2017
  7. Appeal decided22 March 2018
  8. Permission expiry21 March 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.