Planning Permission Ireland
GrantedRetentionDecided 19 May 2017

Ballyvaskin South, Miltown Malbay, Co. Clare

Retention of a 30-metre-high telecommunications mast and compound in Miltown Malbay.

17230 · Clare County Council · Lodged 31 March 2017

Reference
17230
Authority
Clare County Council
Register status
Decided
Type
RETENTION
Received
31 March 2017
Residential units
1
Floor area
1 m²

Summary

AI-generated

Retention permission is sought for an existing 30-metre-high telecommunications support structure, including antennas, an equipment container, and associated equipment within a fenced compound and access track. The facility is part of Vodafone Ireland's network.

Retentiontelecomsinfrastructureretention

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

For retention permission ( ref. No. P11-144 ) of an existing development which consists of an existing 30 metre high telecommunications support structure, antennas, equipment container and associated equipment within a fenced compound and access track. The development forms part of vodafone ireland limited's existing gsm and 3g broadband telecommunications network

Key dates

Timeline

  1. Application received31 March 2017
  2. Decision due25 May 2017
  3. Decision issued19 May 2017
  4. Grant issued19 June 2017
  5. Permission expiry18 June 2022

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.