GrantedNew dwellingDecided 31 May 2018

Knockaloaghan, Crusheen, Co. Clare

Demolition of a house and farm building to build a replacement dwelling, garage, and new effluent system.

18276 · Clare County Council · Lodged 9 April 2018

Reference
18276
Authority
Clare County Council
Register status
Decided
Type
PERMISSION CONSEQUENT
Received
9 April 2018
Residential units
1
Floor area
276.88 m²

Summary

AI-generated

Consequent on outline permission, this application seeks to demolish an existing dwelling and farm building. It proposes to construct a replacement dwelling house and garage, relocate the vehicular entrance, and install a new effluent treatment system.

New dwellingdemolitionreplacement homegarageconsequent

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

On the grant of outline permission ( reference no. P17-872), for the following works; (a) demolish existing dwelling, (b) remove existing farm building, (c) construct a replacement dwelling house and garage, (d) relocate existing vehicular entrance and (e) replace existing septic tank, with new effluent treatment system, all with associated site works

Key dates

Timeline

  1. Application received9 April 2018
  2. Decision due3 June 2018
  3. Decision issued31 May 2018
  4. Grant issued1 July 2018
  5. Permission expiry30 June 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.