GrantedEnergyDecided 25 February 2019

Garravagh, Inniscarra, Co. Cork

Construction of a solar farm with 85,000 square metres of panels, a substation, and battery storage for a 35-year lifespan.

187410 · Cork City Council · Lodged 21 December 2018

Reference
187410
Authority
Cork City Council
Register status
Decided
Type
PERMISSION
Received
21 December 2018

Summary

AI-generated

The application seeks permission for a solar farm on ground-mounted frames with a 35-year operational lifespan. The development includes a single-storey substation, six inverter/transformer stations, a battery storage module, security fencing, and CCTV, using an existing entrance.

Energysolarrenewablebattery storageinfrastructure
Storey
1
Floor area
85,000 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Permission for a solar farm consisting of circa 85,000sq. M of solar panels on ground mounted frames, 1 no. Single storey substation, 6 no. Single storey electrical inverter/transformer stations, battery storage module and associated equipment container, security fencing, satellite pole, cctv, and all associated ancillary development works. Construction and operational access to the proposed development will be provided via an existing entrance from the r618 to the south. The operational lifespan of the solar farm will be 35 years.

Land-use zoning

What this land is zoned for

City HinterlandRU
To protect and improve rural amenity and provide for the development of agriculture.

National zoning type: Mixed/general primary sector uses, including 'rural'

Objective set by the Cork City Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received21 December 2018
  2. Decision due25 February 2019
  3. Decision issued25 February 2019
  4. Appeal submitted25 March 2019
  5. Appeal decided10 July 2019

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.