Hollyhill Industrial Estate, Tadhg Barry Road, Hollyhill
Construction of a new substation building for electric car charging points in Hollyhill.
1938803 · Cork City Council · Lodged 17 October 2019
- Reference
- 1938803
- Authority
- Cork City Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 17 October 2019
Summary
AI-generatedPermission is sought to construct a new substation building within the existing car park at Hollyhill Industrial Estate. This infrastructure is designed to cater for additional electric car charging points.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Permission for the construction of a new substation building within the existing car park to cater for additional electric car charging points at the hollyhill industrial estate
Land-use zoning
What this land is zoned for
“To provide for the creation and protection of high technology related office-based industry and enterprise, to facilitate opportunities for employment creation.”
National zoning type: Office, business/technology park and related
Objective set by the Cork City Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planBuilt & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Recent sales nearby
within 500 m| Address | Date | Price | Distance |
|---|---|---|---|
| 120 Ardcullen, Hollyhill, Cork | Nov 2025 | €275,000 | 374 m |
Nearby properties, not this site — a guide to local values.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received17 October 2019
- Decision due11 December 2019
- Decision issued10 December 2019
- Grant issued24 January 2020
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
Permission for the construction of a four storey over partial lower ground floor level office building…
Hollyhill Industrial Estate , Tadgh Barry Road and lands , adjacent to David McCarthy Road and
2241121Cork CityLodged 24 May 2022Commercial
- Granted60 m away
Construction of an extension to the existing car park and all ancillary site development and landscaping works
Hollyhill Industrial Estate, Kilmore Road, Hollyhill, Knocknacullen West
124836corkLodged 20 Apr 2012Infrastructure
- Granted100 m away
Construction of extension to the existing car park and all ancillary site development and landscaping works
Hollyhill Industrial Estate, Kilmore Road, Hollyhill, Knocknacullen West, Co.Cork
135951corkLodged 11 Oct 2013Commercial
- Granted150 m away
Permission for an extension to the entrance lobby of an existing office building and all ancillary site…
Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
1938947Cork CityLodged 9 Dec 2019Commercial
- Granted170 m away
Permission for an extension to an existing office within their existing campus. The proposed office building…
Hollyhill Industrial Estate , Tadgh Barry Road , Holyhill
1636741Cork CityLodged 29 Jan 2016Commercial
- Granted170 m away
Permission for the construction of a new substation building within a car park permitted under Council Ref:…
Hollyhill Industrial Estate , Kilmore Heights , Hollyhill
2342539Cork CityLodged 14 Dec 2023Infrastructure
- Granted180 m away
The construction of an extension to the existing car park and all ancillary site development and landscaping…
Hollyhill Industrial Estate, Kilmore Road, Hollyhill, Knocknacullen West, Co. Cork
164145corkLodged 29 Jan 2016Infrastructure
- Granted180 m away
The construction of an extension to the existing car park and all ancillary site development and landscaping…
Hollyhill Industrial Estate , Kilmore Road , Hollyhill Knocknacullen West
164145Cork CityLodged 29 Jan 2016Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedInfrastructure
Permission for the construction of a new substation building within a car park permitted under Council Ref:…
Hollyhill Industrial Estate , Kilmore Heights , Hollyhill
2342539Cork CityLodged 14 Dec 2023
- GrantedInfrastructure
Permission for a new prefabricated substation building within the existing car park to cater 4no. electric…
Mahon Point Shopping Centre , Mahon , Cork
2443542Cork CityLodged 20 Dec 2024
- GrantedInfrastructure
Permission for proposed new electric vehicle charging facility consisting of 4 separate charging points,…
Aghaboys , Ballymascanlon , Dundalk Co Louth
211306LouthLodged 26 Oct 2021
- GrantedIndustrial
Permission for a) the demolition of an existing ancillary storage unit and sub-station, b) the construction…
Clonakilty Enterprise Park, Cloheen, Clonakilty, Co. Cork
20503corkLodged 18 Sept 2020
- GrantedIndustrial
Permission for (a) the demolition of an existing ancillary storage unit and sub-station, (b) the construction…
Clonakilty Enterprise Park, Cloheen, Clonakilty, Co Cork
15659corkLodged 20 Nov 2015
- GrantedCommercial
Permission is sought for the installation of a modular substation and ancillary site development works; to…
Land Adjacent to Car Park Entrance No. 2, Airside Retail Park, Crowscastle, Swords, Fingal, Co. Dublin
F24A/0392FingalLodged 29 Apr 2024
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.