Planning Permission Ireland
GrantedExtensionDecided 17 August 2023

619 South Circular Road, Dublin 8

Demolition of a garage and construction of a single-storey side extension in Dublin 8.

4010/23 · Dublin City Council · Lodged 23 June 2023

Reference
4010/23
Authority
Dublin City Council
Register status
Decided
Type
Permission
Received
23 June 2023

Summary

AI-generated

Permission is sought for a single-storey side extension with a mono-pitched roof. The works include the demolition of an existing side garage and wall, rebuilding the boundary wall with a relocated vehicular gate, installing a new pedestrian gate, and modifying windows in the existing house.

Extensionextensiondemolitiongarage conversion

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Permission is sought for a single-storey extension (with mono-pitched roof) to the side of 619 south circular road, dublin 8 (at the junction with suir road). The works include the demolition of the existing garage (to the side) and wall; proposed roof-lighting; in the existing house a new porch door and modifications to window openings in the rear return (at ground and first floors levels). The works also include the rebuilding of the boundary wall along suir road (including a replacement, relocated vehicular gate), along with the integration of a new pedestrian gate at the side railings; landscaping generally and miscellaneous other work.

Land-use zoning

What this land is zoned for

Z1: Sustainable Residential NeighbourhoodsRS
To protect, provide and improve residential amenities.

National zoning type: Existing residential

Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 24 March 2025.

Notified floor area: 42.98

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
4 Suirroan, Inchicore, Dublin 8Jul 2025€400,30044 m
Flat 3, 601 South Circular Rd, Dublin 8Oct 2025€126,66761 m
Flat 5, 601 South Circular Rd, Dublin 8Oct 2025€126,66661 m
Flat 4, 601 South Circular Rd, Dublin 8Oct 2025€126,66761 m
Flat 2, 601 South Circular Rd, Dublin 8Oct 2025€126,66761 m
Flat 6, 601 South Circular Rd, Dublin 8Oct 2025€126,66661 m
Flat 1, 601 South Circular Rd, Dublin 8Oct 2025€126,66761 m
597 South Circular Rd, Dublin 8, DublinJun 2025€1,100,00073 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received23 June 2023
  2. Decision due17 August 2023
  3. Decision issued17 August 2023
  4. Permission expiry11 November 2028

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.