Planning Permission Ireland
RefusedCommercialDecided 7 February 2024

Belinstown, Ballyboughal, Co Dublin, A41 FV07

Extensions and office redevelopments at a logistics warehousing complex in Ballyboughal.

F23A/0751 · Fingal County Council · Lodged 5 December 2023

Reference
F23A/0751
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
5 December 2023

Summary

AI-generated

The project involves extensions to existing warehouses, including the construction of new office blocks and warehouse extensions. It also includes the partial demolition of one warehouse and the relocation of the northern vehicular site entrance.

Commercialwarehouselogisticsoffice

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Planning permission for extensions to existing warehouses and the replacement of internal offices with new offices as part of the logistic warehousing complex operated by aramex ireland ltd. At belinstown, ballyboughal, co. Dublin, a41 fv07. The proposed development consists of the following
  • Change of use of the existing 2 storey offices to storage within warehouse 1 and 6 and the construction of a new two and part three storey office accommodation to warehouse 1 and 6 (office block 1, c. 1, 683 m2 gfa)
  • Warehouse extension to the east of the existing warehouse 6 (proposed warehouse 9 c. 2,035m2 gfa), and to the south of this warehouse (proposed warehouse 8 c. 478 m2 gfa). Demolition of part of existing warehouse 1 (c. 497 m2 gfa). Change of use of existing mezzanine offices within warehouses 2 and 5 to storage and the provision of new single storey office accommodation (office block 2, c. 323 m2 gfa). Extension to existing warehouse 3 (proposed warehouse 10, c. 2,742 m2 gfa) and new single/ two storey office accommodation (office block 3, c. 1,97 m2). Extension to existing warehouse 4 (proposed warehouse 9, c. 2,041 m2 gfa). The relocation of the northern vehicular site entrance together with modification works consisting of widening of entrance to facilitate a 7.5 m access road, provision for pedestrian access, extension of existing car park with provision of 86 no. Spaces, landscaping and associated lighting and the construction of 1 no. Single storey security hut (c. 19 m2 gfa). The northern entrance will serve all the existing warehouses and warehouse extensions within the development. Demolition of existing dwelling, previously approved for change of use under reg. Ref. F13a/0175 to offices ancillary to the existing logistic complex, to facilitate car parking area to front of new office building. The relocation of the southern vehicular site entrance serving existing 2 storey office building, new facade treatment and window configuration to these offices and extension to existing car park to the south to provide 94 no. Spaces to the south of subject site. Works to include new landscaped areas and berms. Re-alignment of front boundary of subject site to accommodate sightlines at both the northern and southern entrances and associated walls, fencing, gates and landscaping
  • Provision of new 2.4m boundary fencing to the north, east and south boundaries as indicated
  • Provisions of all necessary disabled parking, electric vehicle charging stations and secure bicycle parking provision
  • Hgv waiting parking area with associated dock levellers and circulation space to proposed buildings and provision for truck wash facility. 4.1 no. Esb substation and provision of internal site lighting
  • Provision of new on-site waste water treatment plant (wwtp)
  • All associated site works necessary to facilitate the development, including above and below ground services

Land-use zoning

What this land is zoned for

WD - Warehousing and DistributionWD
Provide for distribution, warehouse, storage and logistics facilities which require good access to a major road network within a good quality environment

National zoning type: Warehouse (excluding retail warehouse)

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received5 December 2023
  2. Decision due7 February 2024
  3. Decision issued7 February 2024
  4. Appeal submitted5 March 2024
  5. Appeal decided24 April 2025

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.