RefusedEnergyDecided 25 November 2024

In the townland of Fieldstown, County Dublin, NA

Construction of a large battery energy storage system facility on a 7-hectare site in Fieldstown.

F24A/0882E · Fingal County Council · Lodged 2 October 2024

Reference
F24A/0882E
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
2 October 2024

Summary

AI-generated

The development consists of a Battery Energy Storage System (BESS) facility within a 7.0-hectare site. It will feature up to 216 containerised battery storage modules, 20 transformer and power conditioning units, a switchgear container, a new access road, security fencing, and an acoustic barrier.

Energybatteryenergybessinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • A battery energy storage system facility within an overall site of 7.0 hectares to include up to 216 no. Containerised battery storage modules on concrete bases, 20no. Transformer and power conditioning units, cable racks, a switchgear container on pedestals and associated lighting, auxiliary transformer and bund
  • Associated development including a new access road to the proposed development and internal access roads, security gates, palisade perimeter security fencing, acoustic barrier, site drainage and attenuation pond, landscaping, car parking and all other works required to facilitate the development

Land-use zoning

What this land is zoned for

RU - RuralRU
Protect and promote in a balanced way, the development of agriculture and rural related enterprise, biodiversity, the rural landscape, and the built and cultural heritage

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Barleyfield, Rolestown, SwordsJul 2025€497,000418 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received2 October 2024
  2. Decision due26 November 2024
  3. Decision issued25 November 2024

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.