GrantedIndustrialDecided 8 March 2021

Newtown, Kilshane Cross, Co. Dublin.

Development of four new warehouses at Kilshane Cross.

FW20A/0126 · Fingal County Council · Lodged 9 February 2021

Reference
FW20A/0126
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
9 February 2021

Summary

AI-generated

The proposed development will comprise the provision of four new warehouses with associated site works.

Industrialwarehouseindustriallogistics
Residential units
4

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The development will comprise the provision of 4 no. Warehouses with m

Land-use zoning

What this land is zoned for

WD - Warehousing and DistributionWD
Provide for distribution, warehouse, storage and logistics facilities which require good access to a major road network within a good quality environment

National zoning type: Warehouse (excluding retail warehouse)

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 1 November 2021. A completion certificate was lodged on 18 July 2023.

Notified floor area: 30.6

12 commencement notices are linked to this development.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received9 February 2021
  2. Further information requested17 December 2020
  3. Further information received9 February 2021
  4. Decision due8 March 2021
  5. Decision issued8 March 2021
  6. Grant issued12 July 2021
  7. Appeal submitted31 March 2021
  8. Appeal decided11 October 2021

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.