GrantedInfrastructureDecided 3 August 2018

BEENNANASPUCK, KILBAHA NORTH KILBAHA MIDDLEKILBAHA SOUTH KILBAHA WEST, GORTDROMASILLAHY GORTDROMAGOWNAGH TOBERATOOREEN

Construction of a 9.95 km underground electricity cable to connect wind farms to the national grid.

171298 · Kerry County Council · Lodged 21 December 2017

Reference
171298
Authority
Kerry County Council
Register status
Decided
Type
PERMISSION
Received
21 December 2017

Summary

AI-generated

The application seeks a 10-year planning permission to lay 9.95 km of underground electrical cables and associated infrastructure. This cable will connect the permitted Beennanaspuck and Toberatooreen wind farms in County Kerry to the national grid via the Athea substation in County Limerick.

Infrastructurewind energygrid connectioninfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

For a 10 years planning permission, to construct an underground electricity cable including associated infrastructure. The proposed underground electricity cable will connect the permitted beennanaspuck wind farm (kerry co. Council planning ref. No. 14/571), (an bord pleanala plannng ref. Pl08.245464) and permitted toberatooreen wind farm (kerry co. Council planning ref. No. 12/431 and 14/854), (an bord pleanala planning ref. Pl08.242170), which are located in co. Kerry, to the national electricity grid via the athea substation in co. Limerick. The development will consist of the laying of 9.95 km of underground electricial cables, associated ducting, associated cable draw pits, electrical cabinets, and excavation / trenching works. The underground electrical cable route is primarily on public road with sections on other road. Details of the underground cables and extent of the works are shown on the planning application drawings. The planning application is accompanied by an environmental impact assessment report (eiar), and also the planning application and environmental impact assessment report

Key dates

Timeline

  1. Application received21 December 2017
  2. Further information requested22 February 2018
  3. Further information received3 April 2018
  4. Decision due5 August 2018
  5. Decision issued3 August 2018
  6. Grant issued6 September 2018
  7. Permission expiry5 September 2028

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.