GrantedInfrastructureDecided 8 August 2016

Southgreen, Kildare, Co. Kildare

Extension of duration for a new modular 38kV electrical transformer station in Kildare.

16623 · Kildare County Council · Lodged 15 June 2016

Reference
16623
Authority
Kildare County Council
Register status
Decided
Type
EXTENSION OF DURATION
Received
15 June 2016

Summary

AI-generated

An extension of duration is sought for the construction of a new modular 38kV electrical transformer station to replace an existing station. The development includes two new power transformers, equipment buildings, outdoor switchgear, and two 13m high towers.

Infrastructureinfrastructuresubstationelectricity

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Extension of duration of planning ref. No. 10/1066 - for a development which will consist of the construction of a new modular 38kv electrical transformer station to replace the existing station to replace the existing station. The new station will comprise; two new bunded 38kv power transformers; two new interface transformers; three new modular equipment buildings; mv outdoor switchgear; 1 x new 13m high tower within the new station and 1 x new 13m high tower in the existing station to replace existing tower; new entrance gates and access road; associated site works

Land-use zoning

What this land is zoned for

Transport and UtilitiesTU
To provide for and improve public utilities.

National zoning type: Electricity

Objective set by the Kildare Town Local Area Plan 2023 - 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
32 Ard Na Pairce Theas, Southgreen Road, Kildare Townprice excludes VATJan 2026€409,692119 m
31 Ard Na Pairce Theas, Southgreen Road, Kildare Townprice excludes VATFeb 2026€396,476122 m
44 The Crescent, Hampden Hillprice excludes VATDec 2025€484,581132 m
2 South Green, KildareJan 2026€725,000163 m
27 The Heights, Walkers Gate, Kildare TownMar 2025€435,000165 m
22 Ard Na Pairce Theas, Southgreen Road, Kildareprice excludes VATDec 2025€409,692167 m
1 Ard Na Pairce Theas, Southgreen Road, Kildare Townprice excludes VATDec 2025€405,286167 m
82 Ard Na Pairce Theas, Southgreen Road, Kildare Townprice excludes VATDec 2025€396,475168 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received15 June 2016
  2. Decision due9 August 2016
  3. Decision issued8 August 2016
  4. Permission expiry9 May 2021

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.