Summary
AI-generatedA 10-year permission is sought for an extension to an existing solar PV farm. The development will consist of approximately 25,300 ground-mounted photovoltaic panels, transformer stations, inverters, and security fencing on an 11.50-hectare site.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A 10 year permission for development on lands which will consist of an extension to the solar pv farm granted permission under register reference 16/1265 comprising the construction of approximately 25,300 no. Photovoltaic panels on ground mounted frames within a site area of 11.50 hectares and associated ancillary development including 4 no. Transformer stations, 4 no. Auxiliary transformer stations, 4 no. Inverters, 1 no. Cctv security camera mounted on 4 metre high pole, perimeter security fencing (2 metres high) and internal access tracks
Key dates
Timeline
- Application received2 November 2017
- Further information requested20 December 2017
- Further information received11 January 2018
- Decision due7 February 2018
- Decision issued6 February 2018
- Grant issued14 March 2018
- Permission expiry13 March 2028
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedEnergy
10 year permission for the development of a solar farm comprising of the installation of a solar pv array…
Knockbrack , Abbeyfeale , Co. Limerick.
19782LimerickLodged 8 Aug 2019
- GrantedEnergy
A 10 year permission for the construction of a Solar PV Energy Development comprising Solar Photovoltaic (PV)…
Fidorfe Grange and part of , Ratoath Manor , Co. Meath
RA170644MeathLodged 9 Jun 2017
- Awaiting decisionEnergy
10 year permission for the construction of an up to 5MWp Solar PV farm, with a maximum export capacity of 4…
Teadies Upper, Enniskeane, Co.Cork,
176172corkLodged 21 Aug 2017
- GrantedEnergy
Ten year permission to develop a Solar farm. This development will consist of installation of Photovoltaic…
Dromsallagh , Cappamore , Co Limerick
17396LimerickLodged 4 May 2017
- GrantedEnergy
For a 10 year permission for the construction of an up to 5MW solar PV farm comprising approximately 20,000…
Ardnehue , Bennekerry , Carlow
16342CarlowLodged 23 Nov 2016
- Awaiting decisionEnergy
A 10 year permission for the erection and operation of a solar photovoltaic energy development. The proposed…
Coolcarrigan , Timahoe West , Co. Kildare
221132KildareLodged 16 Sept 2022
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.