Development of an 8.54km underground grid connection to link a solar farm to a substation.
2660186 · Kilkenny County Council · Lodged 31 March 2026
- Reference
- 2660186
- Authority
- Kilkenny County Council
- Register status
- In progress
- Type
- PERMISSION
- Received
- 31 March 2026
Summary
AI-generatedThe project consists of an 8.54km long 38kV underground electrical cable and associated infrastructure within public roads. This grid connection will transmit electricity from the permitted Kilderry Solar Farm to the existing Kilkenny 110kV substation.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
For the development of a 38kv underground grid connection and all ancillary works at this site situated at: kilderry and adjoining townlands of scart, ballynamona, rathgarvan (or clifden), churchclara, clarabricken, clara upper, clara, kilmagar, feathallagh and ballysallagh co. Kilkenny. The proposed development will consist of:- i. National grid connection in the form of a 38kv underground electrical cable and all associated infrastructure including electrical and communication ducting. The proposed grid connection is c. 8.54km in length, located within the public road (l6657, l6662, l6656, l2616, l6735 and r712) and within the permitted kilderry solar farm (pl. Ref. No. 2360382). The purpose of the proposed grid connection is to transmit electricity from the permitted kilderry solar farm to the existing kilkenny 110kv substation; ii. All associated ancillary site development works including joint bays and communication chambers. The planning application is accompanied by a natura impact statement (nis). The nis assesses both the construction and operation of the proposed development, as well as integral elements of the wider project infrastructure, comprising the permitted kilderry solar farm (pl. Ref. 23/60382) which consists of the construction and operation of a solar photovoltaic (pv) farm located in the townland of kilderry, co. Kilkenny and all associated works. This development is covered by the provisions of the renewable energy directive iii (directive (eu) 2023/2413) and it is important to note that the planning application may be subject to section 34d of the planning and development act 2000, as amended. When a notice issues in accordance with section 34d(b), the provisions of article 26a of the planning and development regulations 2001 to 2025 shall apply.
Key dates
Timeline
- Application received31 March 2026
- Decision due9 December 2026
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Granted310 m away
To provide a new single storey classroom extension with alterations to part of the existing school building…
St Colman's National School , Clarabricken , Clara
18765KilkennyLodged 20 Nov 2018Extension
- Granted310 m away
To provide a new single storey extension to the existing school for an SEN Unit (area 261 sq/meters) with…
St. Coleman's National School , Clarabricken , Clara
21721KilkennyLodged 23 Aug 2021Extension
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
To seek a 10 year planning permission with an operational lifetime of 40 years from the date of commissioning…
Kilderry , and various townlands , Co. Kilkenny
2360372KilkennyLodged 17 Aug 2023
- GrantedEnergy
Kilderry Solar Farm Ltd. seeks a 10 year planning permission with an operational lifetime of 40 years from…
Ground Mounted Solar Array and Ancillary works in the townland of Kilderry Co Kilkenny , Grid connection and associated works within the townland of Kilderry and adjoining townlands of Scart Ballynamona Rathgarvan (or Clifden) Churchclara Clarabricke
2360382KilkennyLodged 25 Aug 2023
- Awaiting decisionEnergy
For a 10 Year Planning Permission for a solar farm with a total area of circa 35 hectares in the townlands of…
townlands of Luffany Murtaghstown Curraghmore , Rathpatrick Ballinlaw and Drumdowney Upper , in County Kilkenny
2660331KilkennyLodged 3 Jun 2026
- Awaiting decisionInfrastructure
(RED III) a 38kV hybrid grid connection cable and is intended to connect the permitted Ballyboughlin Solar…
Townlands of Lehinch Kilcoursey Kilbride Aghamore Raheen and Clara , near Clara , Co. Offaly
2660212OffalyLodged 23 Apr 2026
- Awaiting decisionEnergy
A 10 year planning permission for a solar farm with a total area of circa 51 hectares. The solar farm will…
in the townlands of Ballinure, Ballyoneen, Ballyrobert, Ballyrobert,, Ballysallagh, Caherdesert, Commons, Curraghard, Curraghphlibbode, Desert, Dundullerick East, Dundullerick West,, Lissurla, Mellefontstown, Rathaneague and Rathcobane in County Cork
25/6573corkLodged 25 Nov 2025
- Awaiting decisionInfrastructure
RED III - for development at this site in the townlands of Lehinch, Kilcoursey, Kilbride, Aghamore, Raheen…
Townlands of Lehinch Kilcoursey Kilbride Aghamore Raheen and Clara , near Clara , Co. Offaly
2660105OffalyLodged 4 Mar 2026
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.