RefusedEnergyDecided 22 September 2025

the L5046 and L50462, in the townlands of Cloonanny Glebe Corragarrow, Derryharrow and Gorteenorna

A 10-year permission for two 199.9m wind turbines, a substation, and battery storage in Longford.

2460300 · Longford County Council · Lodged 11 December 2024

Reference
2460300
Authority
Longford County Council
Register status
Appealed
Type
PERMISSION
Received
11 December 2024

Summary

AI-generated

This application seeks a ten-year permission for a wind energy development on a 17.28-hectare site. It includes the demolition of a derelict shed, construction of two 7MW wind turbines with a tip height of 199.9m, an 800m access road, a 32m meteorological mast, a 20kV substation, and a battery energy storage system (BESS).

Energywind farmrenewable energybattery storagedemolition
Floor area
93 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

A ten-year permission for development on lands measuring 17.28ha. The proposed development will consist of the following: (i) demolition of a single-storey derelict shed structure (c. 93 sqm gfa) to facilitate the turbine haul route (ii) construction of two e175 ep5 wind energy converters, each with an electrical rating of 7mw, an overall ground-to-blade tip height of 199.9 metres, a rotor blade diameter of 175 metres, hub height of 112.4 metres, associated foundations and hard-standing areas; (iii) construction of an 800m permanent internal site access road which will run from the l50462 to the wind energy converter hardstanding areas including a 9.1m clear span bridge crossing a local stream; (iv) construction of 1 no. Meteorological mast with a height of 32 metres, associated foundation and hardstanding area; (v) construction of 1 no. 20kv substation compound comprising 2 no. Modular buildings each measuring 13.5 sqm in area and 3.5m in height, a battery energy storage system (bess) comprising 3 storage modules on reinforced concrete plinths, with a height of 2.8 metres and associated electrical works, foundation and hardstanding area; (vi) temporary alterations to the l5046 and l50462 public roads and temporary access roads to facilitate the turbine component haul route, including temporary widening of sections of the l5046 and l50462. (vii) installation of underground collector circuit and communications cabling in underground cable trenches, from the proposed wind energy converter to the proposed on-site substation; (viii) all associated and ancillary site development, excavation, construction, and reinstatement works, including the provision of a temporary construction compound, site drainage, spoil management, fencing, lighting, hedge and tree trimming and cutting and operational maintenance; (ix) this application is seeking a 35- year operational life from the date of commissioning of the entire wind farm. An environmental impact assessment report (eiar) has been prepared in respect of the proposed development

Key dates

Timeline

  1. Application received11 December 2024
  2. Further information requested12 February 2025
  3. Further information received30 July 2025
  4. Decision due23 September 2025
  5. Decision issued22 September 2025
  6. Appeal submitted17 October 2025

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.