Planning Permission Ireland
RefusedEnergyDecided 21 February 2023

Hawkinstown, Riverstown (ED Ardcath) Scatternagh, Balgeeth Ardcath Co. Meath

A 10-year permission for a major solar farm development on a 124-hectare site in Co. Meath.

22552 · Meath County Council · Lodged 27 April 2022

Reference
22552
Authority
Meath County Council
Register status
Decided
Type
PERMISSION
Received
27 April 2022

Summary

AI-generated

The development consists of a solar PV energy development with a total site area of 124.07 hectares. It will include ground-mounted solar panels, inverter/transformer substations, security fencing, and internal access tracks, with an operational lifespan of 35 years.

Energysolarrenewableinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The development will consist of planning permission for a period of 10 years to construct and complete a solar pv energy development with a total site area of 124.07 hectares, to include: inverter/transformer substations, modules, solar pv ground mounted on support structures, temporary construction compounds, internal access tracks, security fencing, electrical cabling and ducting, cctv and other ancillary infrastructure, drainage additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 35-years. A natura impact statement has been prepared in respect of this planning application. Significant further information/revised plans submitted on this application

Land-use zoning

What this land is zoned for

RA - Rural AreaRU
Rural Area

National zoning type: Mixed/general primary sector uses, including 'rural'

Objective set by the Meath County Development Plan 2021-2027 (2021–2027). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received27 April 2022
  2. Further information requested20 June 2022
  3. Further information received8 December 2022
  4. Decision due23 February 2023
  5. Decision issued21 February 2023
  6. Appeal submitted16 March 2023
  7. Appeal decided2 September 2024
  8. Permission expiry1 September 2034

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.