Planning Permission Ireland
GrantedInfrastructureDecided 5 December 2025

Kinnegad - Dunfeirth - Rinawade, Co. Meath

Uprating of a 54km long 110kV overhead electricity line traversing multiple townlands.

2561103 · Meath County Council · Lodged 14 October 2025

Reference
2561103
Authority
Meath County Council
Register status
Decided
Type
PERMISSION
Received
14 October 2025

Summary

AI-generated

EirGrid PLC seeks permission to uprate the existing Rinawade - Dunfirth Tee - Kinnegad 110kV overhead line. The 54 km circuit runs through counties Meath, Kildare, and Offaly, and features 249 supporting structures.

Infrastructuregridelectricityinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Eirgrid plc, with the consent and approval of the electricity supply board (esb), intends to apply for permission for works to uprate the existing rinawade – dunfirth tee – kinnegad 110kv overhead line (ohl). Within county meath, the proposed development will take place within the following townlands: jarretstown, walterstown, moor of meath, rathleek, grange, bogganstown, cappaghcreen, brownstown, salestown, affollus, kilgraigue, harristown, porterstown, kilclone, kimmins, barrockstown, ballymagillin, mulhussey, ferrestown, rodanstown, batterstown, dolanstown, calgath, balfeaghan, kilglin, ferrans, castlejordan, gortnahorna, killaskillen, clongall, knockersally or colehill. The rinawade - dunfirth tee - kinnegad 110 kv ohl circuit runs through county meath, county kildare and county offaly. It is 54 km in length and travels from kinnegad 110 kv substation in killaskillen (county meath) and traverses southeast where a short loop into dunfirth 110 kv substation in dunfirth (county kildare) exists. The line then continues southeast where it terminates at rinawade 110kv substation in rinawade lower (county kildare). The ohl has a total of 249no. Supporting structures. Within the functional area of meath county council, there is 23.16 km of the existing ohl circuit, with 107 no. Structures. Within the functional area of kildare county council there is 30.66 km, with 140 no. Structures, and within the functional area of offaly county council there is 0.42 km, with 2 no. Structures. Separate planning applications will be lodged with kildare county council and offaly county council. The proposed development within co. Meath will comprise
  • The replacement (“restringing”) of the existing ohl circuit conductor wires with a new higher capacity conductor between structure numbers 1
  • 37, 185
  • 214, and 218
  • 223
  • The replacement of angle mast in-situ at 1no. Location, with a new angle mast
  • The strengthening of tower foundations at 3no. Locations
  • The strengthening of towers (i. E. , member replacement) at 5no. Locations
  • The painting of towers at 7no. Locations
  • Shear block remedial works of towers at 1no. Locations
  • The replacement of polesets at 38no. Locations, with similar structures. There will be no change in height at 12no. Poleset replacements. There will be height increases between 0.1m and 2.0m at 26no. Poleset replacements
  • The replumbing of polesets at 11no. Locations
  • The replacement of insulating and ancillary hardware at

Key dates

Timeline

  1. Application received14 October 2025
  2. Decision due8 December 2025
  3. Decision issued5 December 2025
  4. Grant issued5 February 2026
  5. Permission expiry4 February 2031

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.