Planning Permission Ireland
GrantedEnergyDecided 25 July 2017

Doghtog, Crakenstown & Bodeen, Ratoath Co. Meath

Construction of a solar farm with up to 61,600 solar panels on a 52.2-hectare site in Ratoath.

AA161441 · Meath County Council · Lodged 21 December 2016

Reference
AA161441
Authority
Meath County Council
Register status
Decided
Type
PERMISSION
Received
21 December 2016

Summary

AI-generated

The development consists of a solar photovoltaic panel array of up to 61,600 ground-mounted panels. The project includes a 38 kV substation, battery storage, 15 transformer/invertor stations, and associated infrastructure on a 52.2-hectare site.

Energysolarbattery storagesubstationrenewable
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The development of a solar photovoltaic panel array comprising up to 61, 600 no. Solar panels on ground mounted steel frames, 1 no. On site 38 kv substation (consisting of single storey substation control building, transformers, battery storage container and associated cabling and infrastructure), 15 no. Electrical transformer/invertor station modules, underground cable ducts, hardstanding areas, perimeter fencing and security gates, access tracks, cctv and all associated site services and works on a site area of 52.2 hectares, located in the townlands of doghtog, crakenstown and bodeen, ratoath, co. Meath. Permission is also sought for a change of use of the existing entrance from the r155 to facilitate temporary construction access. Permission is sought for 10 years. Significant further information/revised plans submitted on this application

Land-use zoning

What this land is zoned for

RA - Rural AreaRU
Rural Area

National zoning type: Mixed/general primary sector uses, including 'rural'

Objective set by the Meath County Development Plan 2021-2027 (2021–2027). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received21 December 2016
  2. Further information requested20 February 2017
  3. Further information received7 June 2017
  4. Decision due27 July 2017
  5. Decision issued25 July 2017
  6. Grant issued6 September 2017
  7. Permission expiry5 September 2027

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.