Planning Permission Ireland
GrantedEnergyDecided 5 July 2019

Carranstown & Caulstown, Platin, Duleek Co. Meath

A 208MW open cycle gas turbine power plant in Duleek.

LB190031 · Meath County Council · Lodged 17 January 2019

Reference
LB190031
Authority
Meath County Council
Register status
Decided
Type
PERMISSION
Received
17 January 2019

Summary

AI-generated

The development consists of a 208MW electrical output Open Cycle Gas Turbine (OCGT) Peaker Power Plant. It will feature 4 containerised units, exhaust stacks, a water treatment plant, fuel storage tanks, and associated infrastructure.

Energypower plantenergyinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

A 208mw (electrical output) open cycle gas turbine (ocgt) power plant & comprises the following elements: a) 4 no containerised peaker plant units (each 248m2 and c. 8m wide x 31m long x 3.5m high), each housing a fully enclosed & roofed turbo generator comprising of 2no. Turbines with a common generator, all on a concrete plinth of 615m2; b) each unit has two exhaust stacks (15m in height) one for each turbine; c) water treatment plant comprising: 275m2 water treatment (demineralisation) building (6m high x 11m wide x 25m long); a 120m2 raw water treatment tank of 1000m3 (c. 10m high); a 315m2 deionized (treated water) water storage tank (max. Volume of 4900m3) c. 16m high; hydrochloric acid tank (5m3) c. 3m high; sodium hydroxide tank (2.5m3) c. 2m high; waste water storage tank (40m3) (c. 2.5m high); 25m2 firewater module measuring 5m wide x 5m length x 5m high; foul water pump station (slab area of 121m2) d) 2 no fuel storage tanks to each hold a maximum volume of 4,900m3 per tank (each c. 16m high), & associated fuel pumping & filtering equipment & pipework, all within a 2350m2 concrete bund e) 3 no. Waste storage containers, each 80m2 (c. 3m wide x 26m length x 4m high) f) diesel generator with floor area of 32m2 (c. 4m wide x 8m length x 4m high) g) 2 no transformers each 160m2, & each measuring c. 8m wide x 10m length x 9m high h) a 830m2 office & ancillary services building (c. 20 wide x 47 length x 6m high) i) a 570m2 switchgear (mv) building (c. 13 wide x 54 length x 5m high) j) all other miscellaneous & ancillary site works, including:12 no. Car parking spaces & 3no unloading bays, widened & upgraded entrance from the r152, two lowered site platform areas & internal circulation road & hard & soft landscaping, a temporary construction compound, & palisade fencing. K) new road markings, including deceleration lane approaching the site, on the r152. The proposed development will include connection to public water & wastewater provision, supplied by irish water. The application relates to a development which comprises or is for the purposes of an activity requiring an industrial emissions directive (ied) licence & full details of the proposed development & its anticipated environmental impacts will be notified to the environmental protection agency. The proposed development is planned to connect to a new 110kv substation to be located adjacent and to the south-west of the proposed ocgt power plant. A nis accompanies the application. Significant

Land-use zoning

What this land is zoned for

RA - Rural AreaRU
Rural Area

National zoning type: Mixed/general primary sector uses, including 'rural'

Objective set by the Meath County Development Plan 2021-2027 (2021–2027). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Drogheda Rd, Duleek, MeathMay 2026€500,000242 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received17 January 2019
  2. Further information requested13 March 2019
  3. Further information received24 May 2019
  4. Decision due9 July 2019
  5. Decision issued5 July 2019
  6. Appeal submitted31 July 2019
  7. Appeal decided17 December 2019

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.