BALLINDOWN BOGDERRIES, BALLYWILLIAM AND BALLYNAGUILSHA, CO. OFFALY
Construction of a 40MW solar farm with over 122,000 panels, a substation, and associated infrastructure.
20161 · Offaly County Council · Lodged 1 May 2020
- Reference
- 20161
- Authority
- Offaly County Council
- Register status
- Invalid or incomplete
- Type
- PERMISSION
- Received
- 1 May 2020
Summary
AI-generatedThe development consists of a 40MW solar PV array comprising approximately 122,904 photovoltaic panels. It includes a 38kV substation, a transformer unit, 16 power hubs, communications and storage buildings, CCTV cameras, and perimeter fencing across a 70.2-hectare site.
- Storey
- 1
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
The construction of a 40mw solar pv development comprising of a ca. 122,904 no. Photovoltaic panels laid out in arrays, the construction of a 38kv substation (ca. 114.4m2 x 4.75m tall) and a transformer unit (ca. 18m2 x 4m tall) and associated bund, along with ancillary development including: 16 no power hubs (ca. 15.25m2 x 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. Single storey communications building ( 11.1m2 x 2.5m), 1 no. Single storey applicant building (15.25m2 x 2.9m), 1 no. Single storey equipment storage container (7.5m2 x 2.7m), 10 no. Cctv cameras mounted on 4m high poles; and perimeter security fencing. The total development area will be ca 70.2ha
Key dates
Timeline
- Application received1 May 2020
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decisionAt this site
THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF UP TO 40MW COMPRISING OF A…
BALLINDOWN BOGDERRIESBALLYWILLIAM , AND BALLYNAGUILSHA , CO OFFALY
20223OffalyLodged 16 Jun 2020Energy
- Awaiting decisionAt this site
THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF UP TO 40MW COMPRISING OF A…
BALLINDOWN BOGDERRIESBALLYWILLIAM , AND BALLYNAGUILSHA , CO. OFFALY
20190OffalyLodged 22 May 2020Energy
- GrantedAt this site
A 10 YEAR PERMISSION FOR THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF…
BALLINDOWN BOGDERRIES , BALLYWILLIAM AND BALLYNAGUILSHA , CO. OFFALY
21227OffalyLodged 20 Apr 2021Energy
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF UP TO 40MW COMPRISING OF A…
BALLINDOWN BOGDERRIESBALLYWILLIAM , AND BALLYNAGUILSHA , CO. OFFALY
20190OffalyLodged 22 May 2020
- GrantedEnergy
Construction of a Solar PV development with a maximum export capacity (MEC) of up to 122MW comprising of ca.…
Cooleeny , Derryfadda and Killoran , Co. Tipperary
211128TipperaryLodged 30 Jul 2021
- Awaiting decisionEnergy
The construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in…
Kyleagarry Kyle Ballyryan East and Gortdrum , Co. Tipperary
19601384TipperaryLodged 11 Dec 2019
- GrantedEnergy
FOR A PERIOD OF 10 YEARS, TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF…
TRIENEARAGH , DUAGH , CO KERRY
171098KerryLodged 3 Nov 2017
- GrantedEnergy
A 10 YEAR PERMISSION FOR THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF…
BALLINDOWN BOGDERRIES , BALLYWILLIAM AND BALLYNAGUILSHA , CO. OFFALY
21227OffalyLodged 20 Apr 2021
- GrantedEnergy
DEVELOPMENT WILL CONSIST OF A SOLAR PHOTOVOLTAIC (PV) PANEL ARRAY CONSISTING OF UP TO 34,352SQM PV PANELS ON…
STREAMSTOWN , CLAREMORRIS
19903MayoLodged 8 Nov 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.