GrantedEnergyDecided 13 November 2024

Tullamore Distillery Campus Ballard & Clonminch, Tullamore, Co. Offaly

Construction of a 2.6 MWdc solar farm to power the Tullamore Distillery.

2460250 · Offaly County Council · Lodged 3 July 2024

Reference
2460250
Authority
Offaly County Council
Register status
Decided
Type
PERMISSION
Received
3 July 2024

Summary

AI-generated

This application proposes a solar PV development with an installed capacity of up to 2.6 MWdc on a 3.90-hectare site at the Tullamore Distillery Campus. The project will feature approximately 4,100 ground-mounted panels, a transformer station, security cameras, and fencing to provide power directly to the distillery.

Energysolardistilleryrenewable

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The construction of a solar pv development with an installed capacity of up to 2.6 mwdc (mec=0) to provide electrical power to the existing distillery comprising approximately 4,100 no. Photovoltaic panels on ground mounted frames within a site area of 3.90 hectares and associated ancillary development including 1 no. Transformer station, 5 no. Cctv security cameras mounted on 8 metre high poles, perimeter security fencing (2.4 metres high), internal access tracks, extension to existing maintenance access track on the site to the solar pv development, installation of underground cable to connect the transformer station and the distillery and site works required to facilitate the development including the provision of a secondary vehicle access and gate on the northern boundary of the site. The proposed development is for modifications to an establishment to which the major accidents directive applies and is for the purposes of an activity requiring an integrated pollution prevention and control licence

Land-use zoning

What this land is zoned for

Enterprise and EmploymentCOE
This zoning promotes the development of employment uses that reinforce the enterprise and employment function of the subject area as a whole and require high environmental and design standards.

National zoning type: Office, business/technology park and related

Objective set by the Offaly County Development Plan 2021-2027 (2021–2027). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received3 July 2024
  2. Further information requested28 August 2024
  3. Further information received12 September 2024
  4. Decision due14 November 2024
  5. Decision issued13 November 2024
  6. Grant issued18 December 2024
  7. Permission expiry17 December 2029

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.