Townland of Culleenatreen or Flagford, Co. Roscommon
Construction of a 36-metre-high lattice communication structure and associated equipment at an ESB substation.
19396 · Roscommon County Council · Lodged 6 August 2019
- Reference
- 19396
- Authority
- Roscommon County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 6 August 2019
- Residential units
- 1
- Floor area
- 1 m²
Summary
AI-generatedThe development consists of a 36-metre-high free-standing lattice communication structure, including antennae, communication dishes, and ground equipment. The structure will be enclosed within a 2.4-metre-high palisade fence compound at the existing Flagford 220kV substation.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
For the construction of a 36 metre high free standing lattice communication structure and its associated antennae, communication dishes and ground equipment within a 2.4 m high palisade fence compound at esb's existing flagford 220kv substation at
Key dates
Timeline
- Application received6 August 2019
- Further information requested27 September 2019
- Further information received17 April 2020
- Decision due7 April 2021
- Decision issued7 April 2021
- Grant issued12 May 2021
- Permission expiry11 May 2026
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decisionAt this site
For the construction of a 36 metre high free standing lattice communication structure and its associated…
Culleenatreen or Flagford , Co. Roscommon
19328RoscommonLodged 26 Jun 2019Infrastructure
- Granted60 m away
The application site is c.3.0 hectares. Permission is sought for a battery energy storage facility which will…
Culleenatreen or Flagford , Co. Roscommon
187RoscommonLodged 11 Jan 2018Energy
- Awaiting decision90 m away
Permission is sought for a battery energy storage facility which will comprise of rechargeable battery units…
Culleenatreen or Flagford , Co. Roscommon
17517RoscommonLodged 21 Dec 2017Energy
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
For the construction of a 36 metre high free standing lattice communication structure and its associated…
Culleenatreen or Flagford , Co. Roscommon
19328RoscommonLodged 26 Jun 2019
- Awaiting decisionInfrastructure
Erection of 36m high free standing lattice communications structure carrying antennae and communication…
Cowcross, Ballyvoloon, Cobh,
079893corkLodged 26 Jul 2007
- GrantedInfrastructure
For the construction of a 30m metre high, free standing lattice structure, carrying antennae and dishes, with…
Knockalaghta , Ballintober , Co. Roscommon
18145RoscommonLodged 28 Mar 2018
- RefusedInfrastructure
Erection of a 30 metre high, freestanding lattice communications structure, carrying antennae and…
Belgard 38kV Substation, Belgard Road, Tallaght, Dublin 24.
SD06A/0792South DublinLodged 13 Sept 2006
- Awaiting decisionInfrastructure
To construct a 20 metre high free standing monopole communication structure and its associated antennae…
Kilrush Road , Dough , Co. Clare
19418ClareLodged 24 May 2019
- Awaiting decisionInfrastructure
Erection of 36m high free standing lattic communications structure, carrying antennae and communication…
St. Joseph's Rd, Carrigoon Beg, Mallow,
0710586corkLodged 28 Aug 2007
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.