Planning Permission Ireland
GrantedHousing estateDecided 21 April 2026

Carrownanty, Ballymote, Co. Sligo

Construction of 74 houses with associated site works and a new entrance.

2560484 · Sligo County Council · Lodged 19 November 2025

Reference
2560484
Authority
Sligo County Council
Register status
Decided
Type
PERMISSION
Received
19 November 2025

Summary

AI-generated

The development consists of 74 houses, including 7 one-bedroom single-storey dwellings, 15 two-bedroom terraced dwellings, 38 three-bedroom semi-detached dwellings, and 14 four-bedroom semi-detached dwellings. The project also includes communal open spaces, 157 car parking spaces, and a new vehicular entrance.

Housing estatehousing estateresidentialparking
Residential units
74

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • To construct 74 no. Houses and associated site works. The development will consist of the construction of
  • 7 no. One bedroom single storey dwellings
  • 15 no. Two bedroom 2 storey terraced dwellings
  • 38 no. Three bedroom 2 storey semi-detached dwellings
  • 14 no. Four bedroom 2 storey semi-detached dwellings. The proposed development will also include for
  • Provision of communal open space areas to include for natural play spaces and kick about areas
  • Private open spaces, roads & footpaths, public lighting, soft and hard landscaping and revised boundary treatments
  • Proposed new vehicular and pedestrian entrance along the r296 (tubbercurry road), to include for provision of footpath and road setback along the southern edge of the r296, and a pedestrian crossing to the northern edge of the r296, to provide for enhanced connectivity
  • 157 no. Car parking spaces (including e-charging points)
  • Provision for esb substation
  • Connection to public watermain, surface water drainage, together with all associated site works and services
  • Connection to the public sewer along the r296 (tubbercurry road) and provision of on-site pumping station
  • Connection to existing mains water infrastructure and on site surface water drainage works, to serve the development, together with all associated site works and services. A natura impact statement will be submitted to the planning authority with this application

Land-use zoning

What this land is zoned for

nRES – new residential usesR1
Objective: Promote the development of greenfield/infill/backlands for high-quality residential uses such as apartments, houses, sheltered housing and live-work units, retirement homes etc., in tandem with the provision of the required physical infrastruc

National zoning type: New/proposed residential

Objective set by the Sligo County Development Plan 2024-2030 (2024–2030). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
85 Corn Mill Park, Ballymote, Co SligoJul 2025€125,000112 m
82 Corn Mill Park, Ballymote, Mill ParkDec 2025€138,000112 m
4 Castlegrove, Ballymote, SligoApr 2025€226,000121 m
45 Castlegrove, Ballymote, SligoAug 2025€185,000203 m
62 Cornmill, Ballymote, SligoNov 2025€155,000217 m
21 Corn Mill Ballymote, Ballymote, SligoMar 2025€170,000234 m
10 Tower Hill, Ballymote, SligoOct 2025€195,000390 m
17 Tower Hill, Ballymote, SligoMar 2025€155,000416 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received19 November 2025
  2. Further information requested15 January 2026
  3. Further information received26 March 2026
  4. Decision due22 April 2026
  5. Decision issued21 April 2026
  6. Grant issued22 May 2026
  7. Permission expiry21 May 2031

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.