GrantedCommercialDecided 15 October 2015

Grangecastle Business Park, Nangor Road, Clondalkin, Dublin 22.

Construction of a single storey data centre with offices and support facilities in Clondalkin.

SD15A/0133 · South Dublin County Council · Lodged 18 September 2015

Reference
SD15A/0133
Authority
South Dublin County Council
Register status
In progress
Type
Permission
Received
18 September 2015
Floor area
7609 m²

Summary

AI-generated

Permission is sought for a single storey data centre with a gross floor area of approximately 7,609 square metres. The development includes offices, a generator compound, an ESB substation, parking for 60 cars, and associated site works for the sole use of Microsoft Operations Ireland Ltd.

Commercialdata centrecommercialinfrastructure
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Construction of a single storey data centre, with offices (of circa. 1,560sq. M), storage space, computer and associated support areas, electrical component rooms, loading dock area (the building having a total gross floor area of c. 7,609sq. M), roof plant and externally a generator compound (635sq. M), evaporative cooling tank, (150m3) & associated pump house (c. 75sq. M), esb sub station (c. 68sq. M), drivers toilet (c. 5sq. M), smoking shelter and carparking and bicycle facilities for the sole and only use of microsoft operations ireland ltd. In connection with this installation. For site safety purposes the provision of sprinkler tank of c. 737m3 and associated water tank pump room of 75sq. M is proposed. Also included are ancillary site works for connection to existing grange castle infrastructural services as well as fencing, signage, perimeter services road around the building, 60 car parking spaces (including 5 universal accessible car parking spaces) and 18 bicycle spaces. The site perimeter will be enclosed with berming and landscaping to the frontage onto technology park road and the new nangor road. All of the above for the sole use of microsoft operations ireland ltd. An eis (environomental impact statement) has been submitted with this application.

Land-use zoning

What this land is zoned for

EESI
To provide for enterprise and employment related uses

National zoning type: Industrial, enterprise, employment

Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 11 December 2015. A completion certificate was lodged on 25 October 2017.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received18 September 2015
  2. Further information requested13 July 2015
  3. Further information received18 September 2015
  4. Decision due15 October 2015
  5. Decision issued15 October 2015
  6. Grant issued24 November 2015

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.