Glen Lower, Co. Waterford
Installation of a 150-metre overhead power line connection to a new substation in Glen Lower.
19588 · Waterford City and County Council · Lodged 9 August 2019
- Reference
- 19588
- Authority
- Waterford City and County Council
- Register status
- Invalid or incomplete
- Type
- PERMISSION
- Received
- 9 August 2019
Summary
AI-generatedThe application is for a three-phase overhead line connection measuring 150 metres from an existing ESB pole to a new ESB substation. The application is accompanied by a Natura Impact Statement.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A three phase overhead line connection (150m long) from an existing esb pole to the new esb substation including all associated site works, granted under planning reference pd11/314 and pd13/261. A natura impact statement will accompany this application.
Key dates
Timeline
- Application received9 August 2019
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- RefusedAt this site
For a three phase overhead line connection (150m long) including all associated site works, from an existing…
Glen Lower , Co Waterford
19742WaterfordLodged 4 Oct 2019Infrastructure
- RefusedAt this site
Permission for a three phase overhead line connection (150m long) from an existing ESB pole to the new ESB…
Glen Lower , Co Waterford
19734WaterfordLodged 3 Oct 2019Infrastructure
- Awaiting decisionAt this site
A three phase overhead line connection (150m long) including all associated site works, from an existing ESB…
Glen Lower , Co. Waterford
19591WaterfordLodged 12 Aug 2019Infrastructure
- Awaiting decision270 m away
To construct an Underground Anaerobic Digester (4 x 84,000L fibre-glass underground tanks) comprising 1 No.…
Glen Upper & Glen Lower , Kilsheelan , Co. Waterford
17784WaterfordLodged 14 Nov 2017Energy
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
A three phase overhead line connection (150m long) including all associated site works, from an existing ESB…
Glen Lower , Co. Waterford
19591WaterfordLodged 12 Aug 2019
- RefusedInfrastructure
For a three phase overhead line connection (150m long) including all associated site works, from an existing…
Glen Lower , Co Waterford
19742WaterfordLodged 4 Oct 2019
- RefusedInfrastructure
Permission for a three phase overhead line connection (150m long) from an existing ESB pole to the new ESB…
Glen Lower , Co Waterford
19734WaterfordLodged 3 Oct 2019
- Awaiting decisionInfrastructure
Construction of an ESB Medium Voltage substation (standard design) to include an adjacent customer switchroom…
Pembroke Wastewater Pumping Station (WWPS) , Barrowville Kilkenny Road , Carlow
2360304CarlowLodged 19 Dec 2023
- Awaiting decisionInfrastructure
Development on a c. 0.2 ha site, on ESB lands. The development will consist of a physical extension of c. 701…
Lands at the existing Buttevant 38kV Station, Spital Townland, Buttevant, Co. Cork
205187corkLodged 11 Jun 2020
- Awaiting decisionEnergy
Proposed amendments to planning permission Reg. Ref. 17532 to consist of: Replacement of permitted…
Bigbog Coolnabacky Esker , Money Lower Loughteeog , Stradbally Co Laois
2360557LaoisLodged 20 Dec 2023
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.