Planning Permission Ireland
Awaiting decisionDecision due in ~6 weeks (30 August 2026)

South-eastern corner of Waterford & Tramore Racecourse in the Townland of Crobally Upper, at the roundabout between Old Waterford Road and the R675 Tramore Ring Road, Tramore Co. Waterford

Installation of a new booster pumping station and all associated assets below — concrete plinth and above ground kiosk (approx.. 4.6m x 2.6m x 2.1m)

2660495 · Waterford City and County Council · Lodged 6 July 2026

Development description

  • Installation of a new booster pumping station and all associated assets below
  • Concrete plinth and above ground kiosk (approx.. 4.6m x 2.6m x 2.1m)
  • Underground pipework to connect to existing network
  • All ancillary development and site works
  • Associated below ground pipework, fittings and chambers
  • Esb meter cabinet

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
No 8 Ros Mhuire, Crobally Upper, Tramoreprice excludes VATJan 2010€219,00052 m
13 Strand Hill Lane, Strand Hill, Tramoreprice excludes VATJun 2025€338,326145 m
14 Strand Hill Lane, Strand Hill, Tramoreprice excludes VATJun 2025€384,000147 m
16 Strand Hill Lane, Strand Hill, Tramoreprice excludes VATJun 2025€384,000153 m
7 Strand Hill Lane, Strand Hill, Tramoreprice excludes VATAug 2025€333,921171 m
13 Strandhill Green, Strandhill, Tramoreprice excludes VATJul 2025€439,647200 m
11 Strand Hill Green, Strand Hill, Tramoreprice excludes VATMar 2025€431,635218 m
10 Strand Hill Green, Strand Hill, Tramoreprice excludes VATMar 2025€453,744218 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Timeline

  1. Application received6 July 2026
  2. Decision due30 August 2026

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.