GrantedEnergyDecided 26 August 2016

Kilbrannish North, Bunclody, Co. Carlow

Extension of duration for a 2.5MW wind turbine and associated infrastructure.

16218 · Carlow County Council · Lodged 8 July 2016

Reference
16218
Authority
Carlow County Council
Register status
Decided
Type
EXTENSION OF DURATION
Received
8 July 2016

Summary

AI-generated

An extension of duration is sought for the erection of a wind turbine with an 80m hub height and 90m rotor diameter. The project also includes site roads, an electricity substation, and ancillary works.

Energywind energyturbineinfrastructure
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Pl11/280 - to erect a wind turbine, site roads, electricity substation, and ancillary works in the townland of kilbrannish north, bunclody, co. Carlow. The turbine will have a maximum hub height of 80m and a maximum rotor diameter of 90m. The anticipated output will be 2.5mw.

Key dates

Timeline

  1. Application received8 July 2016
  2. Decision due1 September 2016
  3. Decision issued26 August 2016
  4. Permission expiry17 June 2020

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.