GrantedNew dwellingDecided 26 May 2021

Clonmoney West Tld, Hurlers Cross, Newmarket on Fergus

Construction of a new house, shed, and wastewater treatment system in Newmarket on Fergus.

20619 · Clare County Council · Lodged 7 September 2020

Reference
20619
Authority
Clare County Council
Register status
Decided
Type
PERMISSION
Received
7 September 2020
Residential units
1
Floor area
278.8 m²

Summary

AI-generated

The applicant is seeking permission to build a new dwelling house and domestic shed. The project will also include installing a wastewater treatment system and polishing filter, utilizing an existing vehicular entrance.

New dwellingone off houseruralseptic tank

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

For the construction of a dwelling house, shed , wastewater treatment system, polishing filter and to utilise existing vehicular entrance to access site including ancillary site works

The historical record

How new dwellings have been decided in Clare County Council

88% granted

of 2,859 new dwellings granted, refused or part-granted by Clare County Council, 2016–2026.

The same category nationally
81%75,352
All categories in Clare County Council
93%9,526

These are historical figures for this category in this council area, counted from the statutory register over the last 10 years. They are not an assessment of this application and say nothing about how it will be decided.

Land-use zoning

What this land is zoned for

Existing ResidentialRS
The obj. for land zoned ‘existing residential’ is to conserve & enhance the quality and character of the areas, to protect residential amenities and to allow for small scale infill development which is appropriate to the character and pattern of Dev

Objective set by the Shannon Town and Environs Local Area PLan (2012–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received7 September 2020
  2. Further information requested22 October 2020
  3. Further information received15 April 2021
  4. Decision due26 May 2021
  5. Decision issued26 May 2021
  6. Grant issued12 July 2021
  7. Permission expiry11 July 2026

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.