CLOGHERAVADDY & MEENACAHAN, DONEGAL PO, CO. DONEGAL
A ten-year permission for 2.3 kilometres of underground electrical cables to connect a wind farm to the grid.
1650473 · Donegal County Council · Lodged 14 April 2016
- Reference
- 1650473
- Authority
- Donegal County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 14 April 2016
Summary
AI-generatedThe application seeks a ten-year permission to lay 2.3 kilometres of three-phase underground electrical cables in ducts. This infrastructure, which includes communications cables and jointing bays, will connect the permitted Clogheravaddy Wind Farm to the national grid.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A ten year permission for 2.3 kilometres of three phase underground electrical cables laid in ducts, with communications cable, draw pits, jointing bays and associated works. The underground cable will connect the permitted clogheravaddy wind farm to the national grid at esb binbane substation
Key dates
Timeline
- Application received14 April 2016
- Decision due8 June 2016
- Decision issued8 June 2016
- Appeal submitted4 July 2016
- Appeal decided24 November 2016
- Permission expiry23 November 2021
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
A TEN YEAR PERMISSION FOR 2.3 KILOMETRES OF THREE PHASE UNDERGROUND ELECTRICAL CABLES LAID IN DUCTS, WITH…
CLOGHERAVADDY & MEENACAHAN , DONEGAL PO , CO. DONEGAL
1650440DonegalLodged 5 Apr 2016
- GrantedInfrastructure
10 YEAR PERMISSION TO CONSTRUCT AN UNDERGROUND ELECTRICITY CABLE INCLUDING ASSOCIATED INFRASTRUCTURE IN THE…
CUILMORE , GARRYREDMOND , CLOONTOOA
16469MayoLodged 16 Jun 2016
- GrantedInfrastructure
10 YEAR PERMISSION TO CONSTRUCT UNDERGROUND ELECTRICITY CABLE INCLUDING ASSOCIATED INFRASTRUCTURE IN THE…
MAGHERAMORE/SRAH , DERRADDA/CLOONGAWNAGH , CLOONTOOA
16471MayoLodged 16 Jun 2016
- GrantedInfrastructure
DEVELOPMENT OF A 20kv UNDERGROUND GRID CONNECTION CABLE EXTENDING TO CIRCA 6.43KM TO SERVE A PERMITTED WIND…
CARROWLEAGH/GLENREE , BONNYCONLON/CARROWLEAGH , CARROWNAGLOGH/DRUMSHEEN
16822MayoLodged 26 Oct 2016
- GrantedInfrastructure
10 YEAR PLANNING PERMISSION TO CONSTRUCT AN UNDERGROUND ELECTRICITY CABLE INCLUDING ASSOCIATED INFRASTRUCTURE…
CLOONTOOA/GARRYREDMOND/ , KNOCKATOBER/CARTRONNACROSS , BALLINSMAULA/CASTLEGAR/DRUMKEEN
16467MayoLodged 16 Jun 2016
- RefusedEnergy
CONSTRUCT A WINDFARM CONSISTING OF SIX WIND TURBINES WITH AN OVERALL GROUND TO BLADE TIP HEIGHT OF UP TO…
AGHANAGRAN MIDDLE AND LOWER BALLYLINE WEST AND TULLAHENNEL SOUTH BALLYLONGFORD , CO KERRY
19381KerryLodged 12 Apr 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.