Planning Permission Ireland
GrantedInfrastructureDecided 1 November 2016

MAGHERAMORE/SRAH, DERRADDA/CLOONGAWNAGH, CLOONTOOA

Underground electricity cable to connect Magheramore Wind Farm to the national grid.

16471 · Mayo County Council · Lodged 16 June 2016

Reference
16471
Authority
Mayo County Council
Register status
Decided
Type
PERMISSION
Received
16 June 2016

Summary

AI-generated

A 10-year permission is sought to construct a 33kV underground electricity cable and associated infrastructure. This cable will connect the permitted Magheramore Wind Farm to the national grid via the permitted Cloontooa Wind Farm.

Infrastructurewind energygrid connectioninfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

10 year permission to construct underground electricity cable including associated infrastructure in the townlands of magheramore, srah, derradda, cloongawnagh and cloontooa. The proposed 33kv underground electricity cable wiill connect the magheramore wind farm (as permitted under p09/664 & p09/6640 or currently proposed under p13/631 currently under appeal, an bord pleanala ref. P16.244055) to the national electricity grid via the permitted cloontooa wind farm (p09/663, an bord pleanala ref pl16.237401)

Key dates

Timeline

  1. Application received16 June 2016
  2. Further information requested9 August 2016
  3. Further information received8 September 2016
  4. Decision due2 November 2016
  5. Decision issued1 November 2016
  6. Grant issued6 December 2016
  7. Permission expiry5 December 2026

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.