GrantedInfrastructureDecided 17 July 2020

North Wall Power Generating Station, Alexandra Road, Dublin 1

Major alterations and turbine replacements at the North Wall Power Generating Station.

2697/20 · Dublin City Council · Lodged 13 May 2020

Reference
2697/20
Authority
Dublin City Council
Register status
Decided
Type
Permission
Received
13 May 2020

Summary

AI-generated

The development consists of replacing existing indoor gas turbines with more efficient models and replacing a 70m exhaust chimney stack with a 65m stack. It also includes new gas compressors, multiple storage tanks up to 10m tall, a new administration building, and a new entrance on Alexandra Road.

Infrastructurepower stationenergyturbinesinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The development will consist of alterations to the existing north wall power generating station, which include the replacement of existing indoor gas turbines with new and more efficient indoor gas turbines, the replacement of one of the two existing exhaust chimney stack’s (approx. 70m tall) and its re-construction at a reduced height of 65m to mirror the second existing exhaust stack, the installation of new gas compressors with associated fan coolers, the replacement of existing roof-mounted fan coolers, a fuel oil pumphouse, a demineralised water pumphouse, a new 1,000m3 demineralised water tank (approx. 10m tall), a new 1,000m3 gas oil storage tank (approx. 10m tall), the repurposing of an existing 4,000m3 fuel oil storage tank as a demineralised water storage tank of the same volume, a new fire water tank (approx. 10m tall), a new tanker unloading area comprising a concrete pad, emergency diesel generator, a new administration and welfare building, minor modifications to existing surface water drainage, a new entrance opening on to alexandra road and revised internal road layout and minor ancillary plant and equipment structures. The development will also comprise the removal of existing structures including; 70m tall stack and associated boiler, part of the administration building, canteen, stores building and water treatment buildings, gas compressor building as well as a water storage tanks, a bottle storage area and other minor redundant installations. The development will also include all other necessary associated works required to enable the construction and operation of the facility. An environmental impact assessment report (eiar) has been prepared and is submitted as part of the planning application. It should be noted that this facility is identified as a lower tier site under the comah directive, furthermore the facility has an existing industrial emissions licence which is regulated by the environmental protection agency. All required licences and plans will be reviewed as required.

Land-use zoning

What this land is zoned for

Z7: Employment (Heavy)SI
To provide for the protection and creation of industrial uses, and facilitate opportunities for employment creation including Port Related Activities.

National zoning type: General industry

Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received13 May 2020
  2. Decision due17 July 2020
  3. Decision issued17 July 2020
  4. Grant issued28 August 2020

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.