Planning Permission Ireland
GrantedInfrastructureDecided 18 June 2018

Grangegorman Upper and Rathdown Road / Grangegorman Lower junction, public road way, footpaths and car parking areas, Dublin 7

Road realignments and creation of a new public plaza in Grangegorman.

2834/18 · Dublin City Council · Lodged 25 April 2018

Reference
2834/18
Authority
Dublin City Council
Register status
Appealed
Type
Permission
Received
25 April 2018

Summary

AI-generated

The project involves removing a slip lane, realigning a T-junction, and installing new pedestrian crossings. It also includes creating a new public plaza with bicycle parking and landscaping adjacent to a protected boundary wall.

Infrastructurepublic realmplazaroad worksprotected structure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Planning permission comprising: removal of existing one-way left turn slip lane to grangegorman upper; realignment of the t-junction with rathdown road / grangegorman lower; new raised pedestrian shared surface on grangegorman lower with 2 no. Uncontrolled pedestrian crossings; 1 no. Pedestrian crossing on rathdown road and associated new road surface treatment and road marking. The development also includes removal of existing parking areas within the junction and creation of a new public plaza with set down area for mobility impaired vehicles, bicycle parking spaces and all associated landscape and site works (including surface treatment, bollards, lighting and feature trees). All development shall take place within a total area of c. 3,516sq. M and is located adjacent to the existing grangegorman boundary wall (a protected structure).

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
65 Rathdown Rd, North Circular Rd, Dublin 7Jan 2025€765,59953 m
25c Rathdown Road, Phibsborough, Dublin 7price excludes VATDec 2025€743,90057 m
66 Rathdown Rd, Phibsoboro, Dublin 7Jun 2026€730,00058 m
25a Rathdown Road (apt 1), Phibsboro, Dublin 7Feb 2025€226,98870 m
25a Rathdown Road (apt 4), Phibsboro, Dublin 7Feb 2025€226,98970 m
25a Rathdown Road (apt 2), Phibsboro, Dublin 7Feb 2025€226,98870 m
25a Rathdown Road (apt 3), Phibsboro, Dublin 7Feb 2025€226,98870 m
20 Orchard Terrace, Grangegorman Upper, Dublin 7Oct 2025€540,000111 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received25 April 2018
  2. Decision due19 June 2018
  3. Decision issued18 June 2018
  4. Grant issued16 January 2019
  5. Appeal submitted17 July 2018
  6. Appeal decided16 January 2019

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.