Planning Permission Ireland
GrantedInfrastructureDecided 29 July 2019

144, Thomas Street, Dublin 8

Demolition of existing boundary walls and construction of a temporary ESB substation on Thomas Street.

2903/19 · Dublin City Council · Lodged 2 May 2019

Reference
2903/19
Authority
Dublin City Council
Register status
Decided
Type
Permission
Received
2 May 2019

Summary

AI-generated

The project involves removing a faux shopfront, partially demolishing existing walls, and constructing a single-storey ESB substation. Temporary permission is sought for a period of five years, including a new boundary wall and vehicular entrance gate.

Infrastructuresubstationdemolitiontemporary
Storey
1
Floor area
37 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The proposed development consists of: (i) removal of an existing faux shopfront to unoccupied site fronting on to thomas street; (ii) partial removal of front boundary wall to thomas street; (iii) partial demolition of walls associated with previously existing building on site; (iv) construction of single storey esb substation (37sq. M); (v) construction of new boundary wall, inclusive of vehicular entrance gate to thomas street; and (vi) all ancillary works necessary to facilitate the development. Permission is sought for a temporary permission of 5 no. Years.

Land-use zoning

What this land is zoned for

Z5: City CentreUC
To consolidate and facilitate the development of the central area, and to identify, reinforce, strengthen and protect its civic design character and dignity.

National zoning type: City/Town/village Centre, central area

Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 19 September 2019.

Notified floor area: 37

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
134 Thomas Street, The Liberties, DublinJan 2025€185,00070 m
134 Thomas Street, The Liberties, DublinSept 2025€550,00070 m
10a Rainsford Ave, Dublin 8, DublinMay 2026€346,00099 m
Apt 7 St Catherines Church, Bridgefoot Street, Dublin 8Feb 2026€323,000100 m
Apt 9 St Catherines Church, Bridgefoot Street, Dublin 8Apr 2025€267,500100 m
Apt 10 St Catherines Church, Bridgefoot Street, Dublin 8Feb 2026€245,000100 m
Apt 14 St Catherines Church, Bridgefoot Street, Dublin 8May 2025€303,000100 m
Apt 5 St Catherines Church, Bridgefoot Street, Dublin 8May 2025€250,000100 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received2 May 2019
  2. Further information requested26 June 2019
  3. Further information received2 July 2019
  4. Decision due29 July 2019
  5. Decision issued29 July 2019
  6. Grant issued9 September 2019

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.