Poolbeg Generating Station, Pigeon House Road, Dublin 4
Demolition of three buildings and construction of a 75 MW battery energy storage system at Poolbeg Generating Station.
3625/20 · Dublin City Council · Lodged 23 October 2020
- Reference
- 3625/20
- Authority
- Dublin City Council
- Register status
- Decided
- Type
- Permission
- Received
- 23 October 2020
Summary
AI-generatedThis application seeks permission to demolish three disused modern buildings with a combined floor area of 3,240 sq.m. In their place, a 75 MW capacity battery energy storage system (BESS) facility will be constructed within a secured compound, alongside remediation and cladding works on adjacent buildings.
- Floor area
- 3,240 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Planning permission for development on a c. 5.3 ha site located within the existing poolbeg generating station, pigeon house road, dublin 4 (eircode d04 xd82), which is licenced by the environmental protection agency (epa) under an industrial emissions (ie) licence [ref. P0577-03]. The development will consist of: (a) the demolition of three existing disused modern buildings with a combined floor area of 3,240 sq. M. Comprising: (1) a single storey [up to 3.6 m high], c. 166 sq. M. Safety centre (pavilion) building; (2) a single storey [up to 4.5 m high], c. 463 sq. M. Store building; (3) a multi-storey [up to 20 m high], c. 2,611 sq. M. Store / workshop building; (b) works including: (1) remediation and cladding of exposed northern façade of 5-storey [up to 20.4 m high], redundant former administration building; (2) cladding of exposed western façade of turbine hall building on eastern boundary of development site; (3) ancillary site clearance, grading and surfacing; (c) construction and operation of a 75 mw capacity battery energy storage system (bess) facility within a secured compound including the following elements: (1) up to 24 battery container unit arrangements comprising: 24 concrete plinths (c. 110 sq. M. , c. 0.5 m high) typically supporting battery containers (c. 2.6 m high); air conditioning (a/c) unit (c. 1.8 m high); inverter unit (c. 3.8 m high); battery transformer unit (c. 3.3 m high); ring main unit (rmu) (c. 3.3 m high); (2) a c. 126 sq. M. , c. 4.7 m high control building; (3) industrial/ electrical plant including: (i) 3 lightning monopoles (c. 20 m high); (ii) scada communication mast (c. 18 m high); (iii) var support unit on concrete plinth (c. 24 sq. M. , c. 3.4 m high); (iv) 2 bunded house transformers (c. 19.8 sq. M. , c. 3.2 m high); (v) spare parts storage container (c. 36 sq. M. , c. 2.6 m high); (vi) fenced transformer compound (c. 1,309 sq. M. , c. 5.6 m high); (vii) cable trays (and associated service connections); (viii) pole mounted security cameras (c. 8.3 m high); (4) removal of existing fencing and gates, and installation of: various boundary and internal fencing and gates with different treatments including palisade specification (c. 2.6 m high), and chainlink specification (c. 2.7 m high); (5) ancillary development works including provision of areas of hardstanding, internal access roads, onsite drainage and attenuation, temporary construction laydown areas; and connections to site services networks including: telecommunications, electrical, water supply, surface water drainage/ attenuation, and ancillary cabling. The primary access will be via the existing poolbeg generating station entrance at pigeon house road with a temporary construction access via the existing entrance off the road immediately south of the poolbeg generating station. An environmental impact assessment report (eiar) which complies with the european union (planning and development) (environmental impact assessment) regulations 2018 (s. I. 296 of 2018) will be submitted to the planning authority with the application. A natura impact statement (nis) will be submitted to the planning authority with the application. The eiar and nis will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy, during office hours at the offices of the planning authority. The planning application may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of dublin city council during its public opening hours and a submission or observation in relation to the application may be made to the authority in writing on payment of the prescribed fee within the period of 5 weeks beginning on the date of receipt by the authority of the application. The application may also be viewed or downloaded on the department of housing, planning and local government's eia portal located at https://housinggovie. Maps. Arcgis. Com/apps/webappviewer/index. Html? Id=d7d5a3d48f104ecbb206e7e5f84b71f1.
Land-use zoning
What this land is zoned for
“To provide for the protection and creation of industrial uses, and facilitate opportunities for employment creation including Port Related Activities.”
National zoning type: General industry
Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planBuilt & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Built — construction complete
A commencement notice records works starting on 8 April 2022. A completion certificate was lodged on 9 March 2023.
Notified floor area: 23 m²
2 commencement notices are linked to this development.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received23 October 2020
- Further information requested17 December 2020
- Further information received15 March 2021
- Decision due7 May 2021
- Decision issued7 May 2021
- Grant issued22 June 2021
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Granted100 m away
The proposed development will consist of — Demolition of the existing Babcock Store building; 1 No. Hydrogen…
Lands within the Poolbeg Generating Station complex, Pigeon House Road, Dublin 4, D04 XD82
3137/23Dublin CityLodged 31 Jan 2023Energy
- Granted120 m away
The Electricity Supply Board (ESB) intends to apply for planning permission for development on a c. 5.6 ha…
Poolbeg Generating Station, Pigeon House Road, Dublin 4 (Eircode D04 XD82)
3624/20Dublin CityLodged 23 Oct 2020Energy
- Granted130 m away
Permission for works to an existing above ground natural gas installation. The development will consist of…
Poolbeg Power Station, Pigeon House Road, Dublin 4
WEB1928/25Dublin CityLodged 27 Apr 2025Infrastructure
- Invalid130 m away
Planning Permission for works to an existing above ground Natural Gas Installation - the construction of 1…
Poolbeg Power Station, Pigeon House Rd, Dublin 4
WEB2681/24Dublin CityLodged 10 Dec 2024Infrastructure
- Granted130 m away
Planning Permission for the construction of 1 no. 8 m CCTV pole and all associated works
Poolbeg Power Station, Pigeon House Road, Dublin 4
WEB2703/24Dublin CityLodged 12 Dec 2024Infrastructure
- Invalid130 m away
Permission for works to an existing above ground natural gas installation. The development will consist of…
Poolbeg Power Station, Pigeon House Road, Dublin 4
WEB1605/25Dublin CityLodged 21 Mar 2025Infrastructure
- Invalid130 m away
Permission for works to an existing above ground natural gas installation. The works will consist of the…
Poolbeg Power Station, Pigeon House Rd, Dublin 4
WEB1532/25Dublin CityLodged 13 Mar 2025Infrastructure
- Granted130 m away
The development will consist of 1 no. gas analyser kiosk, minor road extension, rooftop-mounted solar panels,…
Poolbeg AGI, Poolbeg Power Station, Pigeon House Road, Dublin 4
WEB2574/25Dublin CityLodged 3 Jul 2025Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedEnergy
Planning permission for development on a c. 3.5 ha site bounded by Shellybanks Road to the east and by South…
Dublin Bay Power Station, Pigeon House Road, Dublin 4, D04 Y5N2
3646/20Dublin CityLodged 29 Oct 2020
- GrantedEnergy
The Electricity Supply Board (ESB) intends to apply for planning permission for development on a c. 5.6 ha…
Poolbeg Generating Station, Pigeon House Road, Dublin 4 (Eircode D04 XD82)
3624/20Dublin CityLodged 23 Oct 2020
- WithdrawnEnergy
Planning permission for development on a c. 3 ha site located fully within the existing Poolbeg Generating…
Poolbeg Generating Station, Pigeon House Road, Dublin 4
3714/19Dublin CityLodged 9 Aug 2019
- GrantedEnergy
Planning permission for development on a c. 6.1 ha site to the south of the existing Dublin Bay Power…
Dublin Bay Power Station, Pigeon House Road, Dublin 4, D04 Y5N2
3647/20Dublin CityLodged 29 Oct 2020
- WithdrawnDemolition
Planning permission for development on a 1.1 hectare site located fully within the existing Poolbeg…
a 1.1 hectare site located fully within the existing Poolbeg Generating Station, Pigeon House Road, Dublin 4 (Eircode D04 XD82)
4247/19Dublin CityLodged 18 Oct 2019
- WithdrawnEnergy
C. 3.2 ha site bounded by Shellybanks Road to the east and by South Bank Road to the south; being also to the…
c. 3.2 ha site bounded by Shellybanks Road to the east and by South Bank Road to the south, Pigeon House Road, Dublin 4, D04 Y5N2
4015/19Dublin CityLodged 17 Sept 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.