Planning Permission Ireland
RefusedCommercialDecided 29 November 2023

Plot 3, Old Corduff Road, Blanchardstown Corporate Park 2, Ballycoolin, Dublin 15

Change of use from a permitted warehouse to a data centre in Blanchardstown.

FW23A/0184 · Fingal County Council · Lodged 7 November 2023

Reference
FW23A/0184
Authority
Fingal County Council
Register status
Appealed
Type
Permission
Received
7 November 2023

Summary

AI-generated

The development consists of a change of use of a previously permitted warehouse/logistics unit to a data centre. It includes a first-floor mezzanine for data storage, an office expansion, a plant floor level, and roof-level air handling units.

Commercialdata centreindustrial parkmezzanine

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Data centre - servecentric intends to apply for permission for development to amend a previously permitted scheme (reg. Ref. Fw22a/0038) at this c. 0.76 ha site known as plot 3, old corduff road, blanchardstown corporate park 2, ballycoolin, dublin
  • The development will consist of the change of use of the permitted warehouse/logistics unit to a data centre, including: a minor increase in site area (c. 42 sq m); the reduction in floor area at ground floor level (c. 360 sq m); the provision of a double height delivery bay at ground floor level; the provision of a first-floor level mezzanine (c. 2,574 sq m) to include data storage floorspace and ancillary uses; the increase in floor area of the ancillary office at ground and first floor level (c. 340 sq m); the provision of a plant floor level (c. 377 sq m) located above the ancillary office floorspace; the provision of air handling units (ahu), variable refrigerant flow (vrf) condenser units and solar panels at roof level; revisions to the staircore and lift arrangements of the ancillary office at ground floor and first floor level and the provision of a stairwell extending to the plant floor level and roof level; the provision of 2 no. Staircores located to the north-east and south-west of the building; the provision of a medium voltage transformer enclosure adjoining the south-east building elevation at ground floor level and all associated alterations to the north-east, south-east and south-west building elevations (the maximum building height permitted under reg. Ref. Fw22a/0038 will decrease from c. 16.9m to c. 14.5m. The gross floor area of the previously permitted building will increase by c. 2,931 sq m to c. 6,524 sq m primarily due to the inclusion of the first-floor level mezzanine). The development will also include: modifications to the hgv service yard to include the provision of enclosed bio-diesel (hvo) standby generators, 2 no. Flue stacks (c. 19m in height), a sprinkler tank and a pump house; minor alterations to the permitted car parking areas, resulting in a total of 36 no. Car parking spaces (an increase of 1 no. Car parking space), including 4 no. Electric vehicle (ev) spaces and 2 no. Accessible spaces; increase in the bicycle parking provision (64 no. Short and long terms spaces in total); provision of 4 no. Motorcycle spaces; the provision of a 2m shared pedestrian and cyclist pathway linking the old corduff road to the adjoining lands to the south-east, including associated access gates, site lighting, boundary treatments and landscaping; the provision of security gates at the 2 no. Permitted vehicular entrances; modifications to landscaping areas and perimeter fencing; relocation of waste management areas and all associated site excavation and development works above and below ground. Ai rcvd 07/11/2023

Land-use zoning

What this land is zoned for

GE - General EmploymentSI
Provide opportunities for general enterprise and employment

National zoning type: Industrial, enterprise, employment

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received7 November 2023
  2. Decision due4 December 2023
  3. Decision issued29 November 2023
  4. Appeal submitted4 January 2024
  5. Appeal decided21 May 2025

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.