Planning Permission Ireland
GrantedHousing estateDecided 15 February 2018

SHRONEDARRAGH, BARRADUFF, KILLARNEY

Completion of an unfinished housing development in Barraduff, including 78 houses, a creche, and retention of 8 houses.

17980 · Kerry County Council · Lodged 2 October 2017

Reference
17980
Authority
Kerry County Council
Register status
Decided
Type
RETENTION
Received
2 October 2017
Residential units
86
Floor area
86 m²

Summary

AI-generated

Permission is sought to complete an unfinished development in Barraduff. The project includes constructing 72 semi-detached houses, 6 terraced houses, a creche, and an all-weather play area, alongside outline permission for 5 detached houses and retention of 8 semi-detached houses.

Housing estatehousing estatecrecheretentionunfinished estate
Storeys
2

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Complete the unfinished development commenced under planning reg 05/2462. Planning permission to; (1) construct 72 no. Two storey semi detached houses of varying layouts (2) construct two blocks of three unit , two storey houses (six no. Houses in total), (3) construct a new pedestrian access on to the r570. (4) to construct a creche; (5) construct an all weather surface play area. Outline planning permission to construct five detached two storey houses. Retention permission to retain and complete the construction of 8 no. Semi detached houses and boundaries (commenced under pl 05/2462) at sites nos. 23 to
  • Retention permission to retain, modify and complete the construction of access roads, services and ancillary works commenced under planning reg 05/2462 and including the construction of an additional storm connection and retention permission for an esb substation as constructed

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
2 Blackthorn Close, Barradubh Village, Killarneynot full market priceDec 2025€200,00079 m
12 Blackthorn Close, Barraduff, Killarneyprice excludes VATOct 2025€325,991102 m
11 Blackthorn Close, Barraduff, Killarneyprice excludes VATNov 2025€325,991106 m
10 Blackthorn Close, Barraduff, Killarneyprice excludes VATDec 2025€325,991113 m
8 Blackthorn Close, Barraduff, Killarneyprice excludes VATNov 2025€325,991126 m
Apt 3 Barraduff Village, Barraduff Village, KillarneyDec 2025€235,000162 m
21-28 An Fhaice Mhor, Shronedarragh, Barraduffprice excludes VATJun 2025€1,867,841242 m
4 Fuschia Lane, Barraduff, KillarneyJan 2026€340,000314 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received2 October 2017
  2. Further information requested23 November 2017
  3. Further information received20 December 2017
  4. Decision due15 February 2018
  5. Decision issued15 February 2018
  6. Grant issued22 March 2018
  7. Appeal submitted14 March 2018
  8. Appeal decided20 September 2018
  9. Permission expiry21 March 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.