Planning Permission Ireland
GrantedEnergyDecided 12 June 2023

BALLYENAGHTY KERRIES EAST LOHERCANNOR, FARRANSTEPHEN KNOCKANACUIG BALLYVELLY, TRALEE

Infrastructure works for the consented Ballyenaghty Solar Farm including a substation building and underground cabling.

23425 · Kerry County Council · Lodged 18 April 2023

Reference
23425
Authority
Kerry County Council
Register status
Decided
Type
PERMISSION
Received
18 April 2023

Summary

AI-generated

The development includes a 60 sq.m substation building, a modular structure within a fenced compound, and a 2.3km underground cable connecting the solar farm to the existing Ballyrickard substation. A Natura Impact Statement will be submitted with the application.

Energysolarinfrastructuresubstation
Floor area
72 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

(a) provision of an mv substation building (c. 60sq. M, 4.6m high) and an mv modular structure ( c. 12sq. M, 3.4 m high) both being within a fenced compound within the "consented ballyenaghty solar farm" (b) a c. 2.3km 10kv underground cable installation between the " consented ballyenaghty solar farm and the existing esb ballyrickard 38kv substation via the kerries road and spa road and (c) all other ancillary works. Planning permission is sought for a duration of 10 years. A natura impact statement (nis) will be submitted with the application

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
The Kerries, Tralee, KerryJun 2026€500,000235 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received18 April 2023
  2. Decision due12 June 2023
  3. Decision issued12 June 2023
  4. Grant issued14 July 2023
  5. Permission expiry13 July 2033

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.