GrantedEnergyDecided 13 September 2023

BALLYMACASY COOLNAGRAIGUE BALLYLINE EAST, BALLYLINE WEST, LEANAMORE AND DROMALIVAUN

A 10-year permission for a 146.6-hectare solar farm across three land parcels in County Kerry.

23284 · Kerry County Council · Lodged 16 March 2023

Reference
23284
Authority
Kerry County Council
Register status
Decided
Type
PERMISSION
Received
16 March 2023

Summary

AI-generated

The application seeks a 10-year permission and 40-year operation for a solar farm spanning 146.6 hectares. The development includes 794,430 square meters of solar panels, inverter stations, control buildings, and an underground connecting cable route.

Energysolarrenewableinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Apply for a 10 year permission and 40 year operation for a solar farm of 146.6 hectares, on 3 no. Land parcels consisting as described herin: west parcel( ballymacasy, ballyline east and ballyline west townlands) c 58.48 hectares, central parcel ( coolnagraigue townland) c. 53.8 hectares and east parcel ( leanamore and dromalivaun townlands) c 34.32 hectares, a route corridor for an under ground internal electrical cable connecting the west and central parcels to the east parcel consisting of c 3772 meters in length. The total site area for the proposed development is c. 146.6 hectares and consists of the following: 794,430 sq meters of solar photovoltaic panels on ground mounted steel frames, inverter/transformer stations, underground power and communication cables and ducts, boundary security fencing, 2 no. Medium voltage (mv) control buildings, new internal access tracks and associated drainage infrastructure, upgrade of 1 no. Site entrance off the lio12 local road and 1 no. New site entrance off the l 6021 local road, cctv/lighting posts, 5 no. Culvert crossings, biodiversity enhancement, landscaping and all associated site services and works. Installations of an internal network cable comprise trenching for an underground medium voltage electrical cable and associated joint bays and infrastructure, for a distance of approximately 35 metres in length along the l6021 and approximately 3,737 metres within the solar farm lands. As part of a separate strategic infrastructure development (sid) planning application , provision of a 110kv electrical substation woth electrical controlbuilding, associated compound with palisade fence and 2 no. Overhead line masts, will be lodged with an bord pleanala in due course. The proposed substation is to be located in the east parcel in the townland of dromalivaun with connection to the existing overhead lines in either the east parcel in the townland of dromalivaun or the central parcel in the townland of lenamore. A natura impact statement (nis) has been prepared in relation to the project and accompanies this planning application .

Key dates

Timeline

  1. Application received16 March 2023
  2. Further information requested9 May 2023
  3. Further information received20 July 2023
  4. Decision due13 September 2023
  5. Decision issued13 September 2023
  6. Grant issued17 October 2023
  7. Permission expiry16 October 2028

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.