GrantedEnergyDecided 28 November 2023

Brannockstown Brownstown Carnalway Coghlanstown West, Corbally Delamain Dunnstown Gaganstown Greenhills, Harristown Hillsborough Moorhill & Rochestown

A 10-year planning permission for a massive 246-hectare solar farm across multiple townlands in Kildare.

23567 · Kildare County Council · Lodged 26 May 2023

Reference
23567
Authority
Kildare County Council
Register status
Decided
Type
PERMISSION
Received
26 May 2023

Summary

AI-generated

The proposed solar farm will feature ground-mounted solar panels with a surface area of 1,130,000 square metres and a maximum export capacity of 210 megawatts. The development includes 40 inverter stations, electrical cabling, security fencing, and access tracks with an operational lifespan of 40 years.

Energysolarrenewableinfrastructure
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

10 year planning permission for a solar farm with a total area of circa 246 hectares in the townlands of brannockstown, brownstown, carnalway, coghlanstown west, corbally, delamain, dunnstown, gaganstown, greenhills, harristown, hillsborough, moorhill and rochestown in county kildare. The solar farm will consist of solar photovoltaic panels with a surface area of 1,130,000m2 on ground mounted frames, 40 no. Single storey electrical inverter/transformer stations, 4 no. Single storey spare parts containers, 19 no. Ring main units, 9 no. Weather stations underground electrical ducting and cabling within the development site, private lands and within the l6063, l2032, l6071, r448, l6072, r412, l6074, l6047 and r413 public roads to connect solar farm field parcels, security fencing, cctv, access tracks, 5 no. Stream and drain deck crossings, temporary construction compounds, landscaping and all associated ancillary development and drainage works. Construction and operational access will be via entrances from the r412, r413, l6044, l6047 and l6063. The solar farm will have a maximum export capacity of circa 210 megawatts. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. Part of the proposed development is situated within the demesne land of harristown house which contains protected structures, but no works are proposed to these protected structures but no works are proposed to these protected structures. Revised by significant further information consisting of revised site layout plans to reduce panelled areas in parcels 1 and 2, relocation of meteorological mast in parcel 1 and all associated landscaping and ancillary works

Key dates

Timeline

  1. Application received26 May 2023
  2. Further information requested19 July 2023
  3. Further information received24 October 2023
  4. Decision due28 November 2023
  5. Decision issued28 November 2023
  6. Grant issued20 August 2024
  7. Appeal submitted2 January 2024
  8. Appeal decided20 August 2024
  9. Permission expiry19 August 2029

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.