GrantedEnergyDecided 12 July 2021

Townlands of Rossmore and Clogrennan, Co. Laois.

Installation of underground cabling and a substation to connect the Bilboa Wind Farm.

20281 · Laois County Council · Lodged 11 June 2020

Reference
20281
Authority
Laois County Council
Register status
Decided
Type
PERMISSION
Received
11 June 2020

Summary

AI-generated

The project involves installing approximately 6.6km of underground cables and a new substation across the Carlow and Laois borders. It also includes upgrading forestry tracks, constructing access tracks, and widening roads to facilitate turbine delivery.

Energywind energygrid connectioninfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Installation of approximately 4.6 kilometers ('km') of underground cables within carlow county council ('ccc') boundary and approximately 2.0km within laois county council ('lcc') boundary with a voltage of up to 38 kilovolts and associated works, including a new substation with lcc, for the connection of the consented bilboa wind farm (planning register references : carlow county council 11/154; an bord pleanala pl 01.240245) to the national electricity grid; upgrading of an existing forestry track within ccc; construction of two new onsite access track within ccc; re-orientation and increasing in size of a crane hardstanding area within ccc; and road strengthening and widening along an updated turbine delivery route, within lcc, pursuant to the consented bilboa wind farm (planning register references: carlow county council 11/154; an bord pleanala pl 01.240245). The application is accompanied by a planning report, environmental impact assessment report and a natura impact statement

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Upper Rossmore, Killeshin, CarlowApr 2025€535,000371 m
Rossmore Upper, CarlowNov 2025€530,000415 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received11 June 2020
  2. Further information requested4 August 2020
  3. Further information received4 May 2021
  4. Decision due13 July 2021
  5. Decision issued12 July 2021
  6. Grant issued19 August 2021
  7. Permission expiry18 August 2026

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.