GrantedEnergyDecided 10 December 2019

townlands detailed above

Addition of four wind turbines up to 150 metres tall to an existing fifteen-turbine wind farm.

1926 · Leitrim County Council · Lodged 8 February 2019

Reference
1926
Authority
Leitrim County Council
Register status
Decided
Type
PERMISSION
Received
8 February 2019

Summary

AI-generated

The development proposes a 30-year planning permission for four new wind turbines with blade tip heights up to 150 metres. The project includes crane hardstands, two substation buildings, underground cabling, access tracks, and a 5 km grid connection.

Energywind energyinfrastructureeiar

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

A thirty year planning permission for an additional four (4) wind turbines to an existing fifteen (15) turbine windfarm. The proposed development will constitute the following: (a) the construction of four (4) wind turbines with hub heights of up to 92 metres with an overall height of up to 150 metres to blade tip. ; (b) the construction of crane hardstand areas located beside each turbine; (c) the construction of two (2) 20 kv substation buildings with associated electrical plant, equipment and security fences; (d) internal windfarm underground cabling; (e) the construction of new site access tracks and the provision of upgraded access roads; (f) installation of a drainage system for the proposed hardstand and road areas; (g) underground grid connection approximately five (5) km in length, predominantly along existing public road network; (h) all associated site development and ancillary works. The planning application is accompanied by an environmental impact assessment report (eiar) and by a natura impact statement in lieu of a thirty year planning permission for an additional six(6) wind turbines to an existing fifteen (15) turbine windfarm in the townlands of lackagh, tullynamoyle, gowlaun and altavra, killarga, county leitrim. The grid connection to corderry substation will be located in the townlands of knockacullion, tawnahoney, lisnagowan, tawnylea, derrintawny, shivdelagh, cloonagh, drumduffy and corderry, killarga county leitrim. The proposed development will constitute the following: (a) the construction of six (6) wind turbines with hub heights of up to 92 metres with an overall height of up to 150 metres to blade tip. ; (b) the construction of crane hardstand areas located beside each turbine; (c) the construction of two (2) 20 kv substation buildings with associated electrical plant, equipment and security fences; (d) internal windfarm underground cabling; (e) the construction of new site access tracks and the provision of upgraded access roads; (f) installation of a drainage system for the proposed hardstand and road areas; (g) underground grid connection approximately five (5) km in length, predominantly along existing public road network; (h) all associated site development and ancillary works. The planning application is accompanied by an environmental impact assessment report (eiar) and by a natura impact statement.

Key dates

Timeline

  1. Application received8 February 2019
  2. Further information requested3 April 2019
  3. Further information received2 October 2019
  4. Decision due10 December 2019
  5. Decision issued10 December 2019
  6. Grant issued28 May 2020
  7. Appeal submitted14 January 2020
  8. Permission expiry27 May 2025

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.